# When is the Mercedes-Benz Places handover date?

URL: https://www.dxbrealtor.ai/answers/mercedes-benz-places-binghatti-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Mercedes-Benz Places by Binghatti has a registered completion date of 31 December 2026 on the Dubai Land Department (DLD) register, the same Q4 2026 date Binghatti gave at launch in December 2023. The tower was 65.25% complete at the last DLD inspection on 28 April 2026. Property Finder now shows completion on 28 February 2027, so the December 2026 date is likely to slip.

## Key figures

- Registered completion date (DLD): 31 Dec 2026 (DLD register via Continental Club)
- Latest construction progress: 65.25% (DLD inspection, 28 Apr 2026)
- Developer's date at launch: Q4 2026 (Metropolitan, 13 Dec 2023; Khaleej Times, 24 Jan 2024)
- Portal estimate now: Feb 2027 (Property Finder, accessed 11 Oct 2026)

## Mercedes-Benz Places handover date: the latest position

The DLD register gives Mercedes-Benz Places a registered completion date of 31 December 2026. That is the same Q4 2026 date Binghatti announced at launch in December 2023. The tower was 65.25% complete at the last DLD inspection on 28 April 2026. More on prices and the plan: [Mercedes-Benz Places by Binghatti](/projects/mercedes-benz-places-binghatti/).

Portals now show a later date. Property Finder lists expected completion on 28 February 2027, and a Dubizzle listing updated on 7 October 2026 shows March 2027. Binghatti has not announced a revised date. With about a third of the work left in April 2026, a handover in the first half of 2027 looks more likely than December 2026.

## Mercedes-Benz Places handover date by building

Mercedes-Benz Places is one tower, listed on the register as "Mercedes-Benz Places Binghatti" (project 2545) with 163 units.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Mercedes-Benz Places Binghatti (163 units) | 65.25% (28 Apr 2026) | 31 Dec 2026 | Q4 2026 at launch; 28 Feb 2027 on Property Finder |

The register shows a gain of 16.76 points between the inspections on 14 October 2025 and 28 April 2026, about 2.6 points a month. At that rate the last 34.75 points would take around 13 months from April 2026. This is a calculation from DLD figures, not a developer forecast.

## How the Mercedes-Benz Places handover date has changed

- **13 December 2023:** Binghatti launches the tower with completion due in Q4 2026 (Metropolitan).
- **15 December 2023:** sales and construction start (Property Finder; DLD register).
- **24 January 2024:** Khaleej Times reports the 341 metre, 65 storey tower "set for completion in the fourth quarter of 2026".
- **14 October 2025 to 28 April 2026:** progress rises by 16.76 points to 65.25% (DLD register).
- **October 2026:** the registered date is still 31 December 2026. Property Finder shows 28 February 2027 and some listings show March 2027.

## What the Mercedes-Benz Places handover date means for payments

The plan on Property Finder and Continental Club is 20% on booking, 50% during construction and 30% on handover. At launch it was sold as 70/30, with the last 30% due on completion (Metropolitan, 13 December 2023). The 30% falls due when the building is completed and handed over, whether that is December 2026 or later. On a 2 bedroom priced from AED 11.5 million on Property Finder in October 2026, that payment would be AED 3.45 million. No post-handover plan has been published.

## What to check before relying on the Mercedes-Benz Places date

1. **The completion date and grace period written in the SPA**, since the registered date of 31 December 2026 is close and portals already show 2027.
2. **The DLD project status for project 2545**, which shows newer inspections as they are recorded. The last public figure is from April 2026.
3. **Which Mercedes-Benz project the unit is in.** The Mercedes-Benz branded towers in Meydan are a separate project with a Q2 2029 estimate on Propsearch.
4. **When the 30% handover payment is called**, and whether an assignment before completion passes that payment to the new buyer.

## Frequently asked

### Is Mercedes-Benz Places finished?

No. It was 65.25% complete at the DLD inspection on 28 April 2026, with a registered completion date of 31 December 2026 (DLD register via Continental Club).

### What is the Mercedes-Benz Places completion date?

31 December 2026 is the registered completion date. Property Finder lists expected completion on 28 February 2027, and some agent listings show March 2027.

### Has the Mercedes-Benz Places handover date been delayed?

Not officially. The DLD register still holds 31 December 2026, in line with the Q4 2026 date given at launch. Portals have moved to Q1 2027, and at the pace recorded between October 2025 and April 2026 the tower would reach 100% around mid 2027.

### When was Mercedes-Benz Places launched?

Binghatti and Mercedes-Benz announced the tower in December 2023, with sales starting on 15 December 2023 (Property Finder). Construction started the same day, according to the DLD register.

## Sources

- Continental Club, Mercedes-Benz Places Binghatti (DLD project register, project 2545), inspection 28 Apr 2026, accessed 11 Oct 2026: https://continentalclub.ae/project/mercedes-benz-places-binghatti-downtown-dubai/
- Continental Club, Dubai handovers in 2026 (DLD project register), accessed 11 Oct 2026: https://continentalclub.ae/handover-2026/
- Metropolitan, Mercedes-Benz Places Binghatti new launch in Dubai, 13 Dec 2023: https://metropolitan.realestate/media/news/mercedes-benz-places-binghatti-new-launch-in-dubai/
- Khaleej Times, Binghatti and Mercedes-Benz launch $1 billion branded residence tower, 24 Jan 2024: https://www.khaleejtimes.com/business/property/dubai-binghatti-mercedes-benz-launch-1-billion-branded-residence-tower
- Property Finder, Binghatti Mercedes-Benz project page, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/binghatti-developers/binghatti-mercedes-benz
- Dubizzle, 2 bedroom listing at Mercedes-Benz Places, listed 2 Jul 2026, updated 7 Oct 2026: https://dubai.dubizzle.com/property-for-sale/residential/apartment/2026/7/2/spacious-burj-and-canal-view-luxurious-2-260007/
- Propsearch, Mercedes-Benz Places Binghatti City (Meydan), accessed 11 Oct 2026: https://propsearch.ae/dubai/mercedes-benz-places-binghatti-city
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status