# When is the Me Do Re Business handover date?

URL: https://www.dxbrealtor.ai/answers/me-do-re-business-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Me Do Re Business has a registered completion date of 20 September 2029 in the DLD project register, and the developer's date is Q3 2029. The last DLD inspection, dated 21 November 2024, recorded the tower 24.47% complete, with the frame built to the eleventh floor. Some portals show Q4 2029, and no newer DLD inspection has been published.

## Key figures

- Registered completion date (DLD): 20 Sep 2029 (DLD project register via Continental Club, accessed 11 Oct 2026)
- Latest construction progress: 24.47% (DLD inspection, 21 Nov 2024)
- Developer's stated date: Q3 2029 (Developer supplied, via Continental Club and Palmera)
- Portal estimate: Q4 2029 (Mitchells, ezre and Property Finder listings, Oct 2026)

## Me Do Re Business handover date: the latest position

Me Do Re Business is registered with the Dubai Land Department for completion on 20 September 2029. Continental Club lists the developer's date as Q3 2029, which agrees with the register. Mitchells, ezre and some Property Finder listings show Q4 2029, one quarter later. Full project details are on the [Me Do Re Business](/projects/me-do-re-business/) page.

The last published DLD inspection, dated 21 November 2024, recorded 24.47%. The register describes the concrete frame as built to the eleventh floor of a tower planned with 39 floors above the ground floor. With about three years left before the registered date, the main open question is progress since that inspection, which the public register does not yet show.

## Me Do Re Business handover date by building

Me Do Re Business is one building, so one date covers all 293 units.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Me Do Re Business (DLD project 3409, Cluster H, plot H1) | 24.47% (21 Nov 2024) | 20 Sep 2029 | Q3 2029 (developer via Continental Club); Q4 2029 (Mitchells, ezre) |

## How the Me Do Re Business handover date has changed

| Date | Event | Source |
|---|---|---|
| 21 Nov 2024 | DLD inspection records 24.47%, frame to the eleventh floor | DLD register via Continental Club |
| 29 Apr 2025 | Sales launch, completion listed as 20 Sep 2029 | Property Monitor via Dubai Office Finder |
| Jul 2025 | First large batch of DLD-registered office sales (17 in July) | Continental Club |
| 15 Nov 2025 | Registered construction start | DLD register via Mitchells |
| Jun 2026 | Eight more sales registered, 8 to 11 June | Mitchells |
| Oct 2026 | Register still shows 20 Sep 2029 | Continental Club, updated 8 Oct 2026 |

The date has not moved since launch. The spread between Q3 and Q4 2029 comes from different sources, not from a revision. The DLD record is unusual in one respect: the inspection date of 21 November 2024 comes a year before the registered construction start of 15 November 2025. The register does not explain this, but its note on the existing frame suggests work on the plot began before the current project was filed.

## What the Me Do Re Business handover date means for payments

Under the 10/40/50 plan published on ezre and Dubainary, half the price falls due on handover. On the AED 4,101,000 entry office that is AED 2,050,500. Five of the eight construction instalments, each 5%, are tied to the tower reaching 40%, 50%, 60%, 70% and 80% construction, so their timing follows actual progress rather than fixed dates. The DLD fee of 4% is paid at booking.

Palmera lists 60/40 plans in which 20% is paid as a down payment and 40% during construction, with either 40% on handover or 10% on handover and 30% spread over one to four years after it. On those plans, a later handover also moves the post-handover instalments later.

## What to check before relying on the Me Do Re Business date

1. **The SPA date and grace period.** Sources differ between Q3 and Q4 2029, and the contract sets which applies.
2. **A current DLD reading.** The public register shows no inspection after 21 November 2024. The Dubai REST app shows the live percentage for project 3409.
3. **Fit-out time after handover.** Offices are delivered core and shell, so an office is usable only after fit-out approval and works, which adds time beyond the handover date.

## Frequently asked

### When will Me Do Re Business be ready?

The DLD register sets 20 September 2029 as the completion date. The developer gives Q3 2029, and some portals show Q4 2029.

### What is the Me Do Re Business completion date?

20 September 2029, as filed with DLD under project number 3409 (Continental Club and Mitchells, register as at 4 to 8 Oct 2026).

### How far along is construction at Me Do Re Business?

DLD recorded 24.47% at its inspection of 21 November 2024. The register describes the concrete frame as built to the eleventh floor of a planned 39 floors above ground. No later inspection is published.

### Has the Me Do Re Business handover date changed?

No change has been recorded. Property Monitor showed 20 September 2029 from the April 2025 sales launch, and the DLD register still shows that date in October 2026. The Q3 versus Q4 2029 difference is between sources, not a revision.

## Sources

- DLD project register via Continental Club, inspection 21 Nov 2024, registry updated 8 Oct 2026: https://continentalclub.ae/project/me-do-re-business-jumeirah-lakes-towers/
- DLD project register via Continental Club, handover 2029 list, accessed 11 Oct 2026: https://continentalclub.ae/handover-2029/
- Mitchells, ME DO RE Business DLD registry and registered sales, registry as at 4 Oct 2026: https://www.mitchellscommercialrealty.com/off-plan/me-do-re-business
- Mitchells, ME DO RE Business offices, accessed 11 Oct 2026: https://www.mitchellscommercialrealty.com/commercial-properties/me-do-re-business
- Dubai Office Finder, Me Do Re Business (Property Monitor data), checked 9 Oct 2026: https://dubaiofficefinder.com/commercial-towers/me-do-re-business-properties/
- ezre, Me Do Re Business payment plan, accessed 11 Oct 2026: https://ezre.ae/projects/me-do-re-business/payment-plan
- Palmera, ME DO RE Business, accessed 11 Oct 2026: https://www.palmera.realestate/property/me-do-re-business/