# When is the MAK I'Sola Bella handover date?

URL: https://www.dxbrealtor.ai/answers/mak-i-sola-bella-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

MAK I'Sola Bella has a registered completion date of 5 September 2027, while MAK Developers still gives Q1 2027. The latest DLD inspection, on 20 August 2026, recorded 27.17% complete. The tower gained about 1.4 points a month in 2026, well short of the pace either date needs.

## Key figures

- Registered completion date (DLD): 5 Sep 2027 (DLD project register via Continental Club)
- Latest construction progress: 27.17% (DLD inspection, 20 Aug 2026)
- Developer's stated date: Q1 2027 (MAK Developers, accessed 11 Oct 2026)
- Progress since April 2026: +5.54 points (23 Apr to 20 Aug 2026, DLD register)

## MAK I'Sola Bella handover date: the latest position

The DLD project register holds a registered completion date of 5 September 2027 for MAK I'Sola Bella. MAK Developers still gives the first quarter of 2027 on its project page, about six months earlier. Prices, sizes and the payment plan are on the [MAK I'Sola Bella](/projects/mak-i-sola-bella/) page.

The latest DLD inspection, on 20 August 2026, recorded 27.17% complete. MAK has not published a revised date, but the inspection record suggests neither date will be met without a sharp rise in pace.

## MAK I'Sola Bella handover date by building

MAK I'Sola Bella is one tower in JVC District 18, DLD project 3096, with 207 units.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| MAK I'Sola Bella (207 units) | 27.17%, 20 Aug 2026 | 5 Sep 2027 | Q1 2027 (MAK Developers; Propsearch); Q3 2027 (Continental Club) |

## How the MAK I'Sola Bella handover date has changed

| Date | What happened | Source |
|---|---|---|
| Sep 2024 | Fact sheet released; handover by Q1 2027 | MAK fact sheet |
| 5 Sep 2024 | Construction start registered | DLD register |
| 29 Nov 2024 | Launch event; 50% due on handover in Q1 2027 | MAK Developers |
| 23 Apr 2026 | DLD inspection records 21.63% | DLD register |
| 20 Aug 2026 | DLD inspection records 27.17% | DLD register |
| Oct 2026 | Register shows completion on 5 Sep 2027; MAK project page still shows Q1 2027 | DLD register; MAK Developers |

The developer has kept Q1 2027 since launch, while the register shows 5 September 2027, exactly three years after the registered start. Between April and August 2026, the tower gained about 1.4 points a month. To reach 100% by 5 September 2027, the remaining 72.83 points would need almost 6 points a month. At the recorded pace, completion would fall in 2030. This is a calculation from the register, not a date given by MAK.

## What the MAK I'Sola Bella handover date means for payments

Half of the price is due on handover under both published plans. The launch plan was 10% on booking, 40% in 5% instalments during construction and 50% on handover, with several instalments on fixed dates through August 2026 (MAK fact sheet). On a studio at the DLD median of AED 685,871, the handover payment is about AED 343,000. On a 1 bedroom at AED 1,062,554, it is about AED 531,000 (Continental Club, register updated 3 October 2026). There is no post-handover plan, so a later handover delays the final payment rather than spreading it.

## What to check before relying on the MAK I'Sola Bella date

1. **Which date the SPA states**, Q1 2027 or 5 September 2027, and the grace period that applies after it.
2. **The next DLD inspections**, measured against the roughly 6 points a month the registered date needs.
3. **Whether remaining instalments are dated or stage-based**, since dated instalments keep falling due even if work slows.
4. **MAK's delivery record**, as this is the first tower from a developer founded in 2023.

## Frequently asked

### When will MAK I'Sola Bella be completed?

The registered completion date in the DLD project register is 5 September 2027. MAK Developers gives Q1 2027. The tower was 27.17% complete on 20 August 2026.

### Is the MAK I'Sola Bella handover date Q1 2027 or Q3 2027?

Both appear. MAK's project page and Propsearch show Q1 2027. The DLD register holds 5 September 2027, and Continental Club shows Q3 2027 on that basis.

### Will MAK I'Sola Bella be delayed?

The progress figures point that way. The tower gained 5.54 points between 23 April and 20 August 2026. Reaching 100% by 5 September 2027 would need almost 6 points a month.

### When did construction start at MAK I'Sola Bella?

The DLD register records 5 September 2024. Propsearch reports a groundbreaking attended by MAK's chief executive, with construction beginning in 2025.

## Sources

- DLD project register via Continental Club, MAK I'Sola Bella, inspection 20 Aug 2026, register updated 4 Oct 2026: https://continentalclub.ae/project/mak-i-sola-bella-jvc-district-18/
- DLD project register via Continental Club, Dubai handover 2027 tracker, accessed 11 Oct 2026: https://continentalclub.ae/handover-2027/
- MAK Developers, MAK I'Sola Bella project page, accessed 11 Oct 2026: https://makdevelopers.com/our-projects/mak-isola-bella/
- MAK Developers, MAK I'sola Bella launch event, 29 Nov 2024: https://makdevelopers.com/isola-bella-launch-event/
- Invest in DXB, MAK I'Sola Bella fact sheet, Sep 2024: https://investindxb.com/wp-content/uploads/2024/09/MAK-ISOLA-BELLA-FACTSHEET-investindxb.pdf
- Propsearch, MAK I'Sola Bella, updated 22 Aug 2026: https://propsearch.ae/dubai/mak-isola-bella
- ezre, I'Sola Bella payment plan, accessed 11 Oct 2026: https://ezre.ae/projects/i-sola-bella/payment-plan
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status