# When is the La Cle by Maaia handover date?

URL: https://www.dxbrealtor.ai/answers/la-cle-by-maaia-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

The DLD register gives La Cle by Maaia a completion date of 14 January 2027, while Maaia gives Q2 2027. A DLD inspection on 29 June 2026 recorded the building 34.57% complete. At the past year's pace, Continental Club estimates completion around June 2028, so both dates may move.

## Key figures

- Registered completion date (DLD): 14 Jan 2027 (DLD project register via Continental Club)
- Latest construction progress: 34.57% (DLD inspection, 29 Jun 2026)
- Developer's stated date: Q2 2027 (Maaia, accessed 11 Oct 2026)
- Estimate at current pace: June 2028 (Continental Club, 2.83 points a month)

## La Cle by Maaia handover date: the latest position

The Dubai Land Department (DLD) register gives La Cle by Maaia a completion date of 14 January 2027. Maaia's own project page gives Q2 2027, as do Propsearch and most listings. Full project details are on the [La Cle by Maaia](/projects/la-cle-by-maaia/) page.

The latest DLD inspection, on 29 June 2026, recorded the building 34.57% complete. At the average pace of the past year, 2.83 points a month, Continental Club estimates completion around 2 June 2028. That estimate assumes the pace stays the same; the March to June 2026 quarter was faster, at about 3.7 points a month.

## La Cle by Maaia handover date by building

La Cle is a single 10 storey building with 58 units in the DLD register.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| La Cle by Maaia | 34.57% (29 Jun 2026) | 14 Jan 2027 | Q2 2027 (Maaia; Propsearch) |

Progress and the registered date are from the DLD project register via Continental Club. Propsearch and Inside Realty give 56 units rather than 58. With one building, every unit carries the same registered date, but the SPA date can still differ by contract.

## How the La Cle by Maaia handover date has changed

| Date | Event | Source |
|---|---|---|
| 16 Dec 2024 | First DLD inspection records 0% | DLD via Continental Club |
| 15 Jan 2025 | Registered construction start | DLD via Continental Club |
| May 2025 | Maaia launches La Clé, handover Q2 2027 | Propsearch; Kotook, 22 May 2025 |
| 26 Mar 2026 | DLD inspection records 23.13% | DLD via Continental Club |
| May 2026 | Propsearch notes construction advancing, handover still Q2 2027 | Propsearch |
| 29 Jun 2026 | DLD inspection records 34.57% | DLD via Continental Club |

Maaia's date has stayed at Q2 2027 since launch. The registered date of 14 January 2027 has not been revised in the register, though the building would need to add about 65 points in six months to meet it.

## What the La Cle by Maaia handover date means for payments

La Cle is sold on a 50/50 plan, with half the price paid on handover (Propsearch; Maaia). On a median 2 bedroom at AED 1,766,940, the handover payment is about AED 883,000. Booking was 10% or 20% depending on the plan (Palmera; Inside Realty). If completion moves later, the handover payment moves with it.

## What to check before relying on the La Cle by Maaia date

1. **Which date the SPA states.** It may say 14 January 2027, Q2 2027 or another date, each with its own grace period.
2. **The latest DLD inspection.** Maaia's own page still showed 25% complete in October 2026, below the June 2026 DLD figure.
3. **Funding for the 50% handover payment**, which on a 3 bedroom with a pool is about AED 1.2 million at the median price.

## Frequently asked

### Is La Cle by Maaia finished?

No. The building was 34.57% complete at the DLD inspection of 29 June 2026 (DLD project register via Continental Club).

### What is the La Cle by Maaia completion date?

The DLD registered completion date is 14 January 2027. Maaia and Propsearch give Q2 2027.

### Has the La Cle by Maaia handover date been delayed?

Maaia's Q2 2027 date has not changed since launch in May 2025. The registered date of 14 January 2027 is earlier than that and is unlikely to be met at 34.57% complete in June 2026.

### How fast is La Cle by Maaia being built?

Progress rose from 23.13% on 26 March 2026 to 34.57% on 29 June 2026. Over the past year Continental Club puts the average at 2.83 points a month.

## Sources

- DLD project register via Continental Club, La Cle by Maaia (inspection 29 Jun 2026), registry updated 7 Oct 2026: https://continentalclub.ae/project/la-cle-by-maaia-al-furjan/
- DLD project register via Continental Club, projects due in 2027, accessed 11 Oct 2026: https://continentalclub.ae/handover-2027/
- Maaia, La Clé project page, accessed 11 Oct 2026: https://maaia.ae/properties/la-cle/
- Propsearch, La Cle by Maaia, updated 16 Apr 2026: https://propsearch.ae/dubai/la-cle-by-maaia
- Kotook, La Clé by Maaia, 22 May 2025: https://kotook.ae/properties/detail/la-cle-maaia-al-furjan-dubai
- Inside Realty, La Clé by Maaia at Al Furjan, accessed 11 Oct 2026: https://insiderealty.ae/en/projects/la-cle-at-al-furjan-west-dubai-by-maaia-developments
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status
