# When is the Imperial Residence handover date?

URL: https://www.dxbrealtor.ai/answers/imperial-residence-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Imperial Residence had a registered completion date of 30 April 2026, and that date has passed without completion. The building was 43% complete at the last published Dubai Land Department inspection on 5 January 2026, and the register still showed that figure on 7 October 2026. The developer's first promise was Q1 2026, and no revised date has been published.

## Key figures

- Registered completion date: 30 Apr 2026 (passed) (DLD project register via Continental Club)
- Latest construction progress: 43% (DLD inspection, 5 Jan 2026)
- Developer's first promise: Q1 2026 (Data Habibi)
- Portal date still shown: Q2 2026 (Property Finder and Data Habibi, Oct 2026)

## Imperial Residence handover date: the latest position

Imperial Residence in Dubai Production City was registered with the Dubai Land Department (DLD) for completion on 30 April 2026. That date has passed. The last published DLD inspection, on 5 January 2026, recorded the eight-storey building 43% complete, and the register still showed 43% and an active status on 7 October 2026 (UAE Property Checker). Prices, sizes and payment plans are on the project page: [Imperial Residence](/projects/imperial-residence/).

No revised date has been published. Property Finder and Data Habibi still showed Q2 2026 in October 2026, a quarter that has already ended. One broker site, Belcato, described the building as handed over in Q2 2026, which conflicts with the register.

## Imperial Residence handover date by building

Imperial Residence is a single building of 137 units in Me'aisem First (DLD project number 3217).

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Imperial Residence (137 units) | 43% (5 Jan 2026) | 30 Apr 2026 (passed) | Q2 2026 (Property Finder, Data Habibi); March 2026 (Propsearch) |

The previous inspection, on 2 June 2025, recorded 20.81%, so the building gained 22.19 points in seven months (DLD project register via Continental Club).

## How the Imperial Residence handover date has changed

| Date | Event | Source |
|---|---|---|
| 1 Jun 2024 | Bookings open. Developer's first promise Q1 2026 | Property Finder; Data Habibi |
| 2 Jun 2024 | Construction start. Registered completion 30 April 2026 | Property Finder; DLD via Continental Club |
| 7 May 2025 | Propsearch estimate: March 2026 | Propsearch |
| 2 Jun 2025 | DLD inspection: 20.81% | DLD via Continental Club |
| 5 Jan 2026 | DLD inspection: 43% | DLD via Continental Club |
| 30 Apr 2026 | Registered completion date passes | DLD via Continental Club |
| 7 Oct 2026 | Register still at 43%, no newer inspection | UAE Property Checker |

The project was planned as a 23 month build. By January 2026, 19 months in, it was 43% complete. Data Habibi records the change from Q1 2026 to Q2 2026 as a postponement, but even Q2 2026 has passed.

## What the Imperial Residence handover date means for payments

Both published plans put 50% of the price on handover: 25/25/50 on Property Finder and 10/40/50 on Data Habibi. With the building unfinished, that payment has not fallen due. On an 849 sq ft 1 bedroom bought for AED 1,199,000 in April 2026, the handover payment would be about AED 600,000. Buyers' payments go into the project escrow account, and the developer draws on it against certified construction progress.

## What to check before relying on the Imperial Residence date

1. **The grace period in the SPA.** The registered date was 30 April 2026, and the SPA sets the buyer's rights once any grace period after that date runs out.
2. **A new DLD inspection.** Nothing has been recorded since 5 January 2026.
3. **Written notice of a revised date from Imperial 55**, since portals still show the expired Q2 2026 target.

## Frequently asked

### When will Imperial Residence be completed?

No current date has been published. The registered completion date of 30 April 2026 has passed, and the building was 43% complete at the last DLD inspection on 5 January 2026.

### Is Imperial Residence finished?

No. The DLD register showed an active, under construction status and 43% progress on 7 October 2026 (UAE Property Checker). One broker website lists it as handed over in Q2 2026, but the register does not support that.

### Has the Imperial Residence handover date been delayed?

Yes. The developer first promised Q1 2026, Propsearch estimated March 2026, and the registered date was 30 April 2026. All three have passed with the building less than half built at the last inspection.

### How fast is construction at Imperial Residence?

The register recorded 20.81% on 2 June 2025 and 43% on 5 January 2026, about three points a month. At that pace, completion would take about 18 more months from January 2026.

## Sources

- DLD project register via Continental Club, Imperial Residence, inspection 5 Jan 2026: https://continentalclub.ae/project/imperial-residence-dubai-production-city/
- DLD project register via Continental Club, handover 2026 list, updated 10 Oct 2026: https://continentalclub.ae/handover-2026/
- UAE Property Checker, Imperial Residence (DLD data), checked 7 Oct 2026: https://uaepropertychecker.com/projects/imperial-residence
- Data Habibi, Imperial Residence IMPZ, accessed 11 Oct 2026: https://datahabibi.ae/dubai/new-projects/imperial-residence-impz
- Propsearch, Imperial Residence IMPZ, updated 7 May 2025: https://propsearch.ae/dubai/imperial-residence-impz
- Property Finder, Imperial Residence project page, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/imperial-55/imperial-residence
- Belcato, Imperial Residence, accessed 11 Oct 2026: https://belcato.com/en/off-plan/project/imperial-residence
