# When is the Haya on the Park handover date?

URL: https://www.dxbrealtor.ai/answers/haya-on-the-park-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Haya on the Park has a registered completion date of 26 February 2027, and Nshama gives Q1 2027. The latest DLD inspection, on 10 September 2026, recorded 35.33% complete. Progress since March 2026 has run at about 2.2 points a month, so a handover by February 2027 would need a pace several times faster.

## Key figures

- Registered completion date (DLD): 26 Feb 2027 (DLD project register via Continental Club)
- Latest construction progress: 35.33% (DLD inspection, 10 Sep 2026)
- Developer's stated date: Q1 2027 (Nshama, via Bayut and Property Finder)
- Progress since March 2026: +12.16 points (25 Mar to 10 Sep 2026, DLD register)

## Haya on the Park handover date: the latest position

The DLD project register holds a registered completion date of 26 February 2027 for Haya on the Park, listed there as Haya On The Park. Nshama gives the first quarter of 2027, and Property Finder, Propsearch and fäm Properties all show February 2027. Prices, sizes and the payment plan are on the [Haya on the Park](/projects/haya-on-the-park/) page.

The latest DLD inspection, on 10 September 2026, recorded 35.33% complete. Nshama has not published a revised date, but the register's progress figures show a building well short of what a February 2027 handover needs.

## Haya on the Park handover date by building

Haya on the Park is a single 14 storey building, DLD project 3050, with 196 units.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Haya on the Park (196 units) | 35.33%, 10 Sep 2026 | 26 Feb 2027 | Q1 2027 (Nshama); Feb 2027 (Property Finder, Propsearch) |

## How the Haya on the Park handover date has changed

| Date | What happened | Source |
|---|---|---|
| 18 Jul 2024 | Sales open; completion set for 26 February 2027 | Property Finder, fäm Properties |
| 4 Nov 2024 | Construction start registered | DLD register |
| 7 May 2025 | Propsearch lists a February 2027 handover | Propsearch |
| 25 Mar 2026 | DLD inspection records 23.17% | DLD register |
| 10 Sep 2026 | DLD inspection records 35.33% | DLD register |

The date has stayed at February 2027 since sales opened. Between 25 March and 10 September 2026, the building gained 12.16 points, about 2.2 points a month. To finish by 26 February 2027, the remaining 64.67 points would need about 11 to 12 points a month. At the recorded pace, the work would run into early 2029. This is a calculation from the register, not a date given by Nshama.

## What the Haya on the Park handover date means for payments

The plan is 10% on booking, 50% during construction and 40% on handover (Bayut; Property Finder; Continental Club). The launch schedule published by Palmera put the construction instalments on fixed dates, the last on 30 September 2026. Buyers on that schedule have paid 60% of the price while the building is about 35% complete. The remaining 40% falls due on handover, so a later handover moves the final payment later. On a 2 bedroom at the DLD median of AED 1,350,888, the handover payment is about AED 540,000 (Continental Club, register updated 3 October 2026).

## What to check before relying on the Haya on the Park date

1. **The completion date and grace period in the SPA**, compared with 26 February 2027 in the register.
2. **The next DLD inspections.** A pace near 2 points a month would leave the building far from complete at the registered date.
3. **Whether Nshama has issued a revised date** to buyers, since none has been published.
4. **Whether a mortgage offer for the 40% handover payment** will still be valid if completion moves past 2027.

## Frequently asked

### When will Haya on the Park be completed?

The registered completion date in the DLD project register is 26 February 2027, and Nshama gives Q1 2027. The building was 35.33% complete on 10 September 2026.

### Is Haya on the Park finished?

No. The DLD inspection of 10 September 2026 recorded 35.33% complete (DLD project register via Continental Club, updated 4 Oct 2026).

### Will Haya on the Park be delayed?

The registered date has not changed, but progress points to a later finish. The building gained 12.16 points between 25 March and 10 September 2026. About 65 points remained with under six months to 26 February 2027.

### When did construction start at Haya on the Park?

The DLD register records a construction start of 4 November 2024. Property Finder gives 19 July 2024, the day after sales opened.

## Sources

- DLD project register via Continental Club, Haya On The Park, inspection 10 Sep 2026, register updated 4 Oct 2026: https://continentalclub.ae/project/haya-on-the-park-town-square/
- DLD project register via Continental Club, Dubai handover 2027 tracker, accessed 11 Oct 2026: https://continentalclub.ae/handover-2027/
- Property Finder, Haya on the Park by Nshama, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/nshama/haya-on-the-park
- Bayut, Haya on the Park building guide, 9 Sep 2025: https://www.bayut.com/buildings/haya-on-the-park/
- Propsearch, Haya on the Park, updated 7 May 2025: https://propsearch.ae/dubai/haya-on-the-park
- Palmera Real Estate, Nshama Haya on the Park, accessed 11 Oct 2026: https://www.palmera.realestate/property/nshama-haya-on-the-park/
- fäm Properties, Haya on the Park, accessed 11 Oct 2026: https://famproperties.com/town-square-dubai/haya-on-the-park
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status
