# When is the Hado by Beyond handover date?

URL: https://www.dxbrealtor.ai/answers/hado-by-beyond-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Beyond gives Q3 2029 for the Hado handover, and the DLD register records a completion date of 30 June 2029. A DLD inspection on 16 June 2026 recorded 0.01% complete, with construction registered to start on 30 June 2026. The project is close to three years from completion, so the date is a plan, not yet a measure of progress.

## Key figures

- Registered completion date (DLD): 30 Jun 2029 (DLD project register via Continental Club)
- Latest construction progress: 0.01% (DLD inspection, 16 Jun 2026)
- Developer's stated date: Q3 2029 (Beyond via Zawya, 30 Dec 2025)
- Registered construction start: 30 Jun 2026 (Data Dubai)

## Hado by Beyond handover date: the latest position

Beyond gives Q3 2029 for the Hado handover, the date it announced at launch on 30 December 2025. The Dubai Land Department (DLD) register records a completion date of 30 June 2029, one quarter earlier. Full project details are on the [Hado by Beyond](/projects/hado-by-beyond/) page.

The latest DLD inspection, on 16 June 2026, recorded the project 0.01% complete, and construction was registered to start on 30 June 2026. No later inspection had been published by 7 October 2026.

## Hado by Beyond handover date by building

Hado has three 21 storey towers, but the DLD register records them as a single project with 692 units and one date.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Hado by Beyond (three towers, one DLD project) | 0.01% (16 Jun 2026) | 30 Jun 2029 | Q3 2029 (Beyond); 30 Sep 2029 (DubaiHaus) |

Progress and the registered date are from the DLD project register via Continental Club, confirmed by Data Dubai.

## How the Hado by Beyond handover date has changed

| Date | Event | Source |
|---|---|---|
| 21 Nov 2025 | First DLD inspection records 0% | Data Dubai |
| 9 Dec 2025 | Project registered with DLD, completion date 30 June 2029 | Data Dubai |
| 30 Dec 2025 | Beyond launches Hado, handover due Q3 2029 | Zawya |
| Jan to Mar 2026 | 514 sales registered in three months | Data Dubai |
| 16 Jun 2026 | DLD inspection records 0.01% | DLD via Continental Club |
| 30 Jun 2026 | Registered construction start | Data Dubai |

The date has not changed since launch. Beyond's earlier Saria tower in Dubai Maritime City gives a guide to its pace: it was 10.32% complete in March 2026, with completion expected in Q1 2028 (Zawya, 24 March 2026).

## What the Hado by Beyond handover date means for payments

Half the price is due on handover. The first half is paid as either 10% on booking and 40% during construction, or 20% in the first month and 30% in six instalments, depending on the source (Continental Club; Ezre). Construction instalments are often linked to dates or progress, so the SPA schedule decides when each falls. The 50% handover payment, about AED 1.29 million on a median 1 bedroom, moves with the handover date.

## What to check before relying on the Hado by Beyond date

1. **The completion date in the SPA.** Three different dates circulate: 30 June 2029, Q3 2029 and 30 September 2029.
2. **How construction instalments are triggered.** If they fall on fixed dates rather than progress, buyers keep paying even if the site moves slowly.
3. **Whether progress has moved above 0.01%.** The next DLD inspection after 16 June 2026 will show how fast work started.
4. **Funding for the 2029 handover payment**, which is half the price on every unit.

## Frequently asked

### When will Hado by Beyond be completed?

The DLD registered completion date is 30 June 2029. Beyond's launch release gave Q3 2029, and some listings give 30 September 2029.

### Has construction started at Hado by Beyond?

Barely. The DLD register shows a construction start of 30 June 2026, and the last published inspection, on 16 June 2026, recorded 0.01%.

### Do all three Hado towers hand over together?

The DLD register treats all three towers as one project with one completion date of 30 June 2029. Beyond has not published separate dates for each tower.

### Has the Hado by Beyond handover date been delayed?

No. The Q3 2029 date given at launch on 30 December 2025 has not changed.

## Sources

- DLD project register via Continental Club, Hado by Beyond (inspection 16 Jun 2026), registry updated 4 Oct 2026: https://continentalclub.ae/project/hado-by-beyond-siora/
- DLD project register via Continental Club, projects due in 2029, accessed 11 Oct 2026: https://continentalclub.ae/handover-2029/
- Data Dubai, Hado By Beyond (DLD inspections), data through 7 Oct 2026: https://datadubai.ae/projects/hado-by-beyond/
- Zawya, BEYOND Developments launches HADO, the first residential project at SIORA on Dubai Islands, 30 Dec 2025: https://www.zawya.com/en/press-release/companies-news/beyond-developments-launches-hado-the-first-residential-project-at-siora-on-dubai-islands-b6tcf541
- DubaiHaus, Hado by Beyond, accessed 11 Oct 2026: https://www.dubaihaus.com/en/project-details/hado-by-beyond-3146
- Ezre, Hado by Beyond payment plan, accessed 11 Oct 2026: https://ezre.ae/projects/hado-by-beyond/payment-plan
- Zawya, BEYOND Developments confirms continued construction progress across Dubai Maritime City masterplan, 24 Mar 2026: https://www.zawya.com/en/press-release/companies-news/beyond-developments-confirms-continued-construction-progress-across-dubai-maritime-city-masterplan-354605
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status