# When is the Guzel Towers handover date?

URL: https://www.dxbrealtor.ai/answers/guzel-towers-handover-date/
Topic: Handover date
Updated: 2026-10-19

## Short answer

The Guzel Towers completion date in the DLD project register is 25 December 2027, and Tiger Properties and Property Finder give Q4 2027. A DLD inspection on 7 October 2026 recorded the project 7.3% complete, up from 6.96% in July 2026. With about 93% of the work left and 14 months to go, the December 2027 date is very likely to move, and Tiger has not published a revised one.

## Key figures

- Registered completion date (DLD): 25 Dec 2027 (DLD project register via Continental Club, 18 Oct 2026)
- Latest construction progress: 7.3% (DLD inspection, 7 Oct 2026)
- Developer's stated date: Q4 2027 (Tiger via Continental Club; Property Finder lists December 2027)
- Progress, July to October 2026: +0.34 points (6.96% on 24 Jul 2026 to 7.3% on 7 Oct 2026)

## Guzel Towers handover date: the latest position

The DLD project register holds 25 December 2027 as the completion date for Guzel Towers, Tiger Properties' twin towers in JVT District 1. Tiger gives Q4 2027 and Property Finder lists December 2027. Prices, sizes and payment plans are on the [Guzel Towers](/projects/guzel-towers/) project page.

The DLD inspection on 7 October 2026 recorded the project 7.3% complete. That leaves about 93% of the work for the 14 months to the registered date. The register has not been updated, and Tiger has not announced a new date.

## Guzel Towers handover date by building

The two towers, Block A and Block B, are registered as one DLD project, so one date and one progress figure cover all 522 units. Property Finder's Phase 2 and Phase 4 listings are sales releases inside the same towers.

| Building or release | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Block A (25 residential floors) | 7.3%, 7 Oct 2026 (whole project) | 25 Dec 2027 | Q4 2027 (Tiger) |
| Block B (5 office and 20 residential floors) | 7.3%, 7 Oct 2026 (whole project) | 25 Dec 2027 | Q4 2027 (Tiger) |
| Guzel Tower Phase 2 release | Same project | 25 Dec 2027 | 30 Dec 2027 (Property Finder) |
| Guzel Towers Phase 4 release | Same project | 25 Dec 2027 | 1 Dec 2027 (Property Finder) |

Source: DLD project register via Continental Club and Mitchell's, project 3458. The towers share two basements, a ground floor with shops and four parking floors.

## How the Guzel Towers handover date has changed

- **1 December 2024:** Bookings open and registered construction start, with completion set for 25 December 2027 (Property Finder; DLD register).
- **9 December 2024:** Tiger announces the launch, with prices from AED 570,000 and five year payment plans.
- **20 December 2024:** First DLD inspection at 0%.
- **30 December 2025:** DLD inspection at 1.19%.
- **13 April 2026:** DLD inspection at 3.56%.
- **24 July 2026:** DLD inspection at 6.96%.
- **7 October 2026:** DLD inspection at 7.3%. The registered date is still 25 December 2027.

The date has not moved since launch, but the build has not kept pace with it. About 22 months after the registered start, the project is about 7% complete. The fastest stretch was April to July 2026, at about 1.1 points a month. Between July and October 2026 it slowed to about 0.14 points a month. Even at the faster spring pace, the remaining work would take about seven years.

## What the Guzel Towers handover date means for payments

Most Guzel Towers buyers pay part of the price at and after handover. On the launch plan, 10% falls due on handover and 20% after it. On the Phase 2 and Phase 4 releases, 10% is due on handover and 30% after it (Property Finder). Construction instalments total 50% on the launch plan and 40% on the later releases. A later handover moves the handover payment and every post-handover instalment later rather than removing them.

## What to check before relying on the Guzel Towers date

1. **The completion date and grace period in the SPA**, compared with the 7.3% DLD figure.
2. **Whether construction instalments follow DLD progress or fixed dates**, since the build is far behind the December 2027 date.
3. **The release named in the SPA.** A Phase 2 or Phase 4 unit can carry a different portal date and a larger post-handover share than a launch unit.
4. **New DLD inspections for project 3458**, through the DLD project status service, for any change in pace or a revised registered date.

## Frequently asked

### When will Guzel Towers be completed?

The registered completion date is 25 December 2027. The towers were 7.3% complete on 7 October 2026, so completion by that date is not realistic on the recorded pace, and no new date has been published.

### Has the Guzel Towers handover date been delayed?

Not formally. The DLD register, Tiger and Property Finder still show December 2027, the date used since bookings opened on 1 December 2024. Progress, though, is well behind what that date needs.

### Do Guzel Towers Block A and Block B hand over on the same date?

Yes, on the register. Both blocks sit under one DLD project, number 3458, with one completion date of 25 December 2027 and one progress figure for the whole project.

### When do Guzel Tower Phase 2 and Phase 4 hand over?

Property Finder lists Phase 2 for 30 December 2027 and Phase 4 for 1 December 2027. These are sales releases inside the same two towers, not separate buildings, so the DLD date of 25 December 2027 applies to them too.

## Sources

- Continental Club, Guzel Towers JVT District 1 (DLD project register), registry updated 4 Oct 2026: https://continentalclub.ae/project/guzel-towers-jvt-district-1/
- Continental Club, project status Dubai (DLD register, CC BY 4.0), updated 18 Oct 2026: https://continentalclub.ae/en/project-status/
- Mitchell's, Guzel Towers (DLD project register), registry as at 23 Sep 2026: https://www.mitchellscommercialrealty.com/off-plan/guzel-towers
- dxbpropy, Guzel Towers Block A (DLD inspection history, project 3458), register as at 14 Oct 2026: https://dxbpropy.ai/offplan/guzel-towers-block-a-jumeirah-village-triangle-b2281
- Tiger Group, Guzel Towers launch announcement, 9 Dec 2024: https://tigergroup.ae/EventsAndNewsDetails/21253
- Property Finder, Guzel Tower by Tiger Group, accessed 19 Oct 2026: https://www.propertyfinder.ae/en/new-projects/tiger-group/guzel-towers
- Property Finder, Guzel Tower Phase 2 by Tiger, accessed 19 Oct 2026: https://www.propertyfinder.ae/en/new-projects/tiger-group/guzel-tower-phase-2-by-tiger
- Property Finder, Guzel Towers Phase 4 by Tiger, accessed 19 Oct 2026: https://www.propertyfinder.ae/en/new-projects/tiger-group/guzel-towers-phase-4-by-tiger
- DLD, real estate project status enquiry: https://dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status
