# When is the Ghaf Woods handover date?

URL: https://www.dxbrealtor.ai/answers/ghaf-woods-handover-date/
Topic: Handover date
Updated: 2026-10-01

## Short answer

Ghaf Woods has no single handover date. The first phases, Serra and Cilia, are listed for Q3 and Q4 2027, and Lacina has a registered completion date of 30 December 2027 on the Dubai Land Department (DLD) register. Later phases run to 2029: Distrikt is registered for 30 September 2028 and Capria East and West for May 2029. At the DLD inspections of 17 August 2026, Cilia was 43.82% built, Serra 42.05% and Distrikt 8.39%. Serra and Cilia have no completion date on the register, and portals give some phases different dates from the DLD.

## Key figures

- Earliest registered completion date (DLD), Lacina: 30 Dec 2027 (DLD register, via Mitchells, 23 Sep 2026)
- Most advanced phase, Cilia: 43.82% (DLD site inspection, 17 Aug 2026 (Serra 42.05% the same day))
- Portal date for the first phases, Serra and Cilia: Q3 to Q4 2027 (Property Finder, accessed 28 Sep 2026)
- Latest registered completion date, Capria East: 15 May 2029 (DLD register, via Mitchells, 28 Sep 2026)

## Ghaf Woods handover date: the latest position

Ghaf Woods does not have one handover date. Majid Al Futtaim registers each phase as a separate project, and the dates run from late 2027 for the first apartment phases to May 2029 for Capria East and West. The furthest along are Cilia, 43.82% built, and Serra, 42.05%, both at DLD inspections on 17 August 2026, and portals list them for Q4 and Q3 2027. More on prices and the community is on the [Ghaf Woods](/projects/ghaf-woods/) page.

The first phases have about a year left to their listed dates with more than half of the work still to do. Serra gained 3.62 points and Cilia 4.28 points between the inspections of 6 July and 17 August 2026. Neither has a completion date on the DLD register yet, so their dates come from portals and the SPA.

## Ghaf Woods handover date by phase

| Phase | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Serra (535 homes, 10 buildings) | 42.05%, 17 Aug 2026 | None on register | Q3 2027 (Property Finder; Data Habibi) |
| Cilia (546 homes, 10 buildings) | 43.82%, 17 Aug 2026 | None on register | Q4 2027 (Property Finder) |
| Lacina (324 homes, 3 buildings) | 20.81%, 6 Jul 2026 | 30 Dec 2027 | Q4 2027 (Property Finder) |
| Distrikt (550 homes) | 8.39%, 17 Aug 2026 | 30 Sep 2028 | Q3 2029 (Property Finder) |
| Capria East (553 homes, 9 buildings) | 0.94%, 23 Jun 2026 | 15 May 2029 | Q3 2028 (Data Habibi) |
| Capria West (714 homes, 12 buildings) | 1.23%, 23 Jun 2026 | 8 May 2029 | Q2 2029 (Data Habibi) |
| Maravelle Residences (96 homes) | Not published | Not found | Q2 2029 (Data Habibi) |

Home counts are from the DLD register, except Maravelle, which is from Data Habibi. Property Finder also lists a villa phase, Arista, for Q4 2027; no matching DLD record was found.

## How the Ghaf Woods handover date has changed

| Date | What happened | Source |
|---|---|---|
| 5 Jun 2024 | Ghaf Woods launched: over 7,000 homes in eight phases to be released by 2031. | Majid Al Futtaim |
| 27 Nov 2024 | Lacina, the second phase, reported sold out. | Majid Al Futtaim, via Amazing Architecture |
| Dec 2024 | Registered construction starts for Lacina (1 Dec) and Serra and Cilia (27 Dec). | DLD register |
| 21 May 2025 | Capria launched as phase three. | Majid Al Futtaim, via mid-east.info |
| Aug to Sep 2025 | Registered starts for Capria West (15 Aug) and Capria East (15 Sep), both due May 2029. | DLD register |
| 8 Jun 2026 | AED 2 billion main contract for Capria East, Capria West and Maravelle awarded to ECC. | Majid Al Futtaim |
| 17 Aug 2026 | Cilia 43.82%, Serra 42.05%, Distrikt 8.39% at DLD inspections. | DLD register |

Sources disagree on two phases. Data Habibi says Capria East's original promise was Q4 2028, now Q3 2028, while the DLD register gives 15 May 2029. One broker lists Lacina for Q4 2028, a year after its registered 30 December 2027.

## What the Ghaf Woods handover date means for payments

Most phases were sold on 10% at booking, 50% during construction and 40% on handover, including Serra, Distrikt, Capria and Maravelle. Continental Club lists Cilia's plan as 60% before completion and 40% on handover. On Serra's AED 1.23 million launch price, the 40% handover payment is AED 492,000, due when that phase completes, which for Serra is listed as Q3 2027.

## What to check before relying on the Ghaf Woods date

1. **Which phase and building the unit is in.** Dates run from Q3 2027 for Serra to May 2029 for Capria East.
2. **The completion date written into the SPA for Serra or Cilia**, since neither has a completion date on the DLD register.
3. **Which date applies for Capria East**, where a portal shows Q3 2028 and the DLD register 15 May 2029.
4. **The DLD project number for the phase** (for example 3076 for Serra, 3016 for Cilia), to read its own inspection figure through DLD's project status service.

## Frequently asked

### When will Ghaf Woods be ready?

Phase by phase. Serra is listed for Q3 2027 and Cilia and Lacina for Q4 2027, with Lacina registered for 30 December 2027. Distrikt is registered for 30 September 2028, Capria West for 8 May 2029 and Capria East for 15 May 2029 (DLD register; Property Finder).

### What is the Ghaf Woods completion date?

There is no single completion date. Majid Al Futtaim plans more than 7,000 homes in eight phases released to 2031, and each registered phase has its own date on the DLD register.

### Is Ghaf Woods finished?

No phase has been handed over. The most advanced, Cilia and Serra, were 43.82% and 42.05% built at the DLD inspections of 17 August 2026.

### When will Serra at Ghaf Woods be ready?

Property Finder and Data Habibi list Q3 2027. The DLD register shows a construction start of 27 December 2024 but no completion date for Serra, and the phase was 42.05% built on 17 August 2026.

### Has the Ghaf Woods handover date been delayed?

No delay has been announced by Majid Al Futtaim. Sources disagree on some phases: Data Habibi lists Capria East for Q3 2028, while the DLD register gives 15 May 2029, and one broker lists Lacina for Q4 2028 against a registered 30 December 2027.

## Sources

- Mitchells Commercial Realty, Serra DLD registry (project 3076), registry as at 23 Sep 2026: https://www.mitchellscommercialrealty.com/off-plan/serra
- Mitchells Commercial Realty, Cilia DLD registry (project 3016), registry as at 23 Sep 2026: https://www.mitchellscommercialrealty.com/off-plan/cilia
- Mitchells Commercial Realty, Lacina DLD registry (project 3336), registry as at 23 Sep 2026: https://www.mitchellscommercialrealty.com/off-plan/lacina
- Mitchells Commercial Realty, Capria East DLD registry (project 3524), registry as at 28 Sep 2026: https://www.mitchellscommercialrealty.com/off-plan/capria-east
- Mitchells Commercial Realty, Capria West DLD registry (project 3525), registry as at 23 Sep 2026: https://www.mitchellscommercialrealty.com/off-plan/capria-west
- Continental Club, Distrikt, Ghaf Woods (DLD project 3503), registry updated 25 Sep 2026: https://continentalclub.ae/project/distrikt-ghaf-woods/
- Continental Club, Cilia, Ghaf Woods (DLD project 3016), registry updated 26 Sep 2026: https://continentalclub.ae/project/cilia-ghaf-woods/
- Continental Club, Lacina, Ghaf Woods (DLD project 3336), registry updated 25 Sep 2026: https://continentalclub.ae/project/lacina-ghaf-woods/
- Data Habibi, Serra, accessed 1 Oct 2026: https://datahabibi.ae/dubai/new-projects/serra
- Data Habibi, Capria East, accessed 1 Oct 2026: https://datahabibi.ae/dubai/new-projects/capria-east
- Data Habibi, Capria West, accessed 1 Oct 2026: https://datahabibi.ae/dubai/new-projects/capria-west
- Data Habibi, Maravelle Residences, accessed 1 Oct 2026: https://datahabibi.ae/dubai/new-projects/maravelle-residences
- Property Finder, Majid Al Futtaim projects in Ghaf Woods, accessed 28 Sep 2026: https://www.propertyfinder.ae/en/new-projects/dev/majid-al-futtaim/dubai/dubai-land-ghaf-woods
- Majid Al Futtaim, launch of Ghaf Woods press release, 5 Jun 2024: https://www.majidalfuttaim.com/en/media-centre/press-releases/detail/2024/06/majid-al-futtaim-announces-its-latest-real-estate-development-bringing-forest-living-to-dubai-with-launch-of-ghaf-woods
- Amazing Architecture, Majid Al Futtaim announces sell-out of Lacina, phase two of Ghaf Woods, 27 Nov 2024: https://amazingarchitecture.com/news/majid-al-futtaim-announces-sell-out-of-lacina-phase-two-of-ghaf-woods
- mid-east.info, Majid Al Futtaim unveils Capria, phase three of Ghaf Woods, 21 May 2025: https://mid-east.info/majid-al-futtaim-unveils-capria-phase-three-of-ghaf-woods-and-achieves-leed-platinum-for-its-newly-opened-sales-experience-centre/
- Majid Al Futtaim, AED 2 billion contract for Capria East and West at Ghaf Woods, 8 Jun 2026: https://www.majidalfuttaim.com/en/media-centre/press-releases/detail/2026/06/majid-al-futtaim-awards-aed-2-billion-contract--marking-major-delivery-milestone-for-ghaf-woods
- Oplus Realty, Majid Al Futtaim projects in Dubai, 27 Apr 2026: https://oplusrealty.com/majid-al-futtaim-projects-dubai/
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status