# When is the Elm at Park Five handover date?

URL: https://www.dxbrealtor.ai/answers/elm-at-park-five-handover-date/
Topic: Handover date
Updated: 2026-10-12

## Short answer

Elm at Park Five is due for handover in June 2027, with a registered completion date of 1 June 2027 in the Dubai Land Department project register. The DLD inspection of 3 September 2026 recorded 16.18% complete. Deyaar's date has not changed since launch, but the two towers would need to build about five times faster than in mid-2026 to meet it.

## Key figures

- Registered completion date (DLD): 1 Jun 2027 (DLD project register via Continental Club, registry updated 1 Oct 2026)
- Latest construction progress: 16.18% (DLD inspection, 3 Sep 2026)
- Developer's stated date: June 2027 (Deyaar factsheet, Nov 2024; Property Finder)
- Change since launch: None (Summer 2027 given at launch)

## Elm at Park Five handover date: the latest position

Elm at Park Five has a registered completion date of 1 June 2027 in the Dubai Land Department (DLD) project register, and Deyaar and Property Finder give June 2027. The DLD inspection of 3 September 2026 recorded 16.18% complete. Full project details are on the [Elm at Park Five](/projects/elm-at-park-five/) page.

The date has been stable since Deyaar opened bookings in October 2024. The pressure is on progress: the last quarter added 5.17 points, while finishing on time would take about 28 points a quarter.

## Elm at Park Five handover date by building

Elm is Towers A and B of Park Five, registered together as one project with one date. The table adds the other Park Five projects with published register data.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Elm at Park Five, Towers A and B (532 units) | 16.18% (3 Sep 2026) | 1 Jun 2027 | June 2027 (Property Finder); summer 2027 (Deyaar) |
| Neem at Park Five | 15.22% (9 Sep 2026) | 1 Dec 2027 | Not published |
| [Ivy at Park Five](/projects/ivy-at-park-five/) (210 units) | 6.28% (17 Sep 2026) | 31 Dec 2027 | Q4 2027 (Deyaar) |

All figures from the DLD register via Continental Club, accessed 11 October 2026. The register does not split Elm's progress between Tower A and Tower B.

## How the Elm at Park Five handover date has changed

| Date | What was stated | Source |
|---|---|---|
| 1 Oct 2024 | Bookings open; June 2027 handover | Aigents Realty |
| 29 Nov 2024 | Factsheet: 50% due on handover in summer 2027 | Deyaar |
| 1 Apr 2025 | Registered construction start; completion date 1 June 2027 | DLD register via Continental Club |
| 10 Jun 2026 | DLD inspection at about 11.01% | DLD register via Continental Club |
| 3 Sep 2026 | DLD inspection at 16.18%; date unchanged | DLD register via Continental Club |

The June figure is derived from the 5.17 point gain Continental Club reports between the two inspections.

## What the Elm at Park Five handover date means for payments

The plan is 10% on booking, 40% during construction and 50% on handover (Deyaar factsheet). Aigents Realty lists the construction instalments as dated payments, ending with 6% in April 2027, so by the registered date most buyers will have paid 50% regardless of progress. The other half moves with completion: about AED 515,000 on a 1 bedroom at the AED 1,030,190 registered median.

## What to check before relying on the Elm at Park Five date

1. **The SPA date and grace period** for the specific tower and unit.
2. **The next DLD inspection.** A 1 June 2027 finish needs about 28 points a quarter, against 5.17 between June and September 2026.
3. **Deyaar's recent timing.** [Regalia](/projects/regalia-by-deyaar/) was handed over in April 2026, about 16 months after its first target, and [Tria](/projects/tria-by-deyaar/) was handed over in October 2026, after its September 2026 target passed (Deyaar, 6 Oct 2026).

## Frequently asked

### What is the Elm at Park Five completion date?

1 June 2027, the completion date for DLD project 3343, Elm At Park Five (via Continental Club). Property Finder shows the same date.

### Has the Elm at Park Five handover date been delayed?

No change has been announced. Deyaar's November 2024 factsheet gave summer 2027, and the register still shows 1 June 2027. A few broker pages quote Q4 2027, which is the date for the later Ivy and Alder buildings.

### Is Elm at Park Five finished?

No. It was 16.18% complete at the DLD inspection of 3 September 2026, up from about 11.01% on 10 June 2026.

### When will the other Park Five buildings be ready?

Neem at Park Five has a registered date of 1 December 2027 and was 15.22% complete on 9 September 2026. Ivy at Park Five has a registered date of 31 December 2027 and was 6.28% complete on 17 September 2026 (DLD register via Continental Club).

## Sources

- Zawya, Deyaar hands over 711 homes at Tria in Dubai Silicon Oasis (press release), 6 Oct 2026: https://www.zawya.com/en/press-release/companies-news/deyaar-builds-on-its-2026-handover-momentum-with-711-new-homes-at-tria-in-dubai-silicon-oasis-1510991
- DLD project register via Continental Club, Elm At Park Five, inspection 3 Sep 2026; registry updated 1 Oct 2026: https://continentalclub.ae/project/elm-at-park-five-dubai-production-city/
- DLD project register via Continental Club, handover 2027 list (Neem and Ivy at Park Five), accessed 11 Oct 2026: https://continentalclub.ae/handover-2027/
- Deyaar, Elm at Park Five factsheet (via Vision-ary), 29 Nov 2024: https://vision-ary.com/wp-content/uploads/2025/01/Elm_Park_Five_by_Deyaar.pdf
- Property Finder, Elm at Park Five project page, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/deyaar-leasing/elm-at-park-five
- Aigents Realty, Elm at Park Five, accessed 11 Oct 2026: https://aigentsrealty.com/areas/dubai-production-city/elm-at-park-five
- My Offplan Investment, Elm at Park Five, accessed 11 Oct 2026: https://myoffplaninvestment.com/property/elm-at-park-five-dubai-production-city-apartments/