Danube's project pages give October 2026 for Elitz 1 and December 2027 for Elitz 2, both later than the dates announced at launch. The Dubai Land Department (DLD) inspection of 13 August 2026 put Elitz 1 at 80.97%, and the inspection of 28 September 2026 put Elitz 2 at 20.01%. The DLD registered completion date for Elitz 1, 31 December 2025, has passed, and Elitz 2 has no registered date.

## Key figures

- Registered completion date (DLD): Elitz 1: 31 Dec 2025 (passed); Elitz 2: none (DLD register, projects 2533 and 2693, via Mitchells, accessed 6 Oct 2026)
- Latest construction progress: 80.97% / 20.01% (Elitz 1 DLD inspection 13 Aug 2026; Elitz 2 DLD inspection 28 Sep 2026)
- Developer's stated date: Oct 2026 / Dec 2027 (Danube project pages for Elitz 1 and Elitz 2, accessed 6 Oct 2026)
- Date at launch: Q4 2025 / Q3 2026 (Gulf News, 30 Dec 2022; Danube, 9 Aug 2023)

## Elitz by Danube handover date: the latest position

Danube Elitz in Jumeirah Village Circle is two separate DLD projects. Danube's project page for Elitz 1 now gives October 2026, and the page for Elitz 2 gives December 2027. The DLD inspection of 13 August 2026 put Elitz 1 at 80.97%, and the inspection of 28 September 2026 put Elitz 2 at 20.01% (Mitchells; Continental Club). Prices and sizes for both phases are on the [Elitz by Danube](/projects/elitz-by-danube/) page.

Elitz 1 is close to finishing: Danube's own inspection on 31 August 2026 recorded 90%, with snagging in progress and the civil defence inspection next. In July 2026 Danube named Elitz 1 among 11 projects due within 12 months (Gulf News, 30 July 2026). Elitz 2 is at an early stage and was not on that list. The newer [Elitz 3 by Danube](/projects/elitz-3-by-danube/) has its own [handover page](/answers/elitz-3-by-danube-handover-date/).

## Elitz by Danube handover date by building

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Elitz 1, Elitz By Danube - 1 | 80.97%, whole project, 13 Aug 2026. Danube: 90%, 31 Aug 2026 | 31 Dec 2025 (passed) | Oct 2026 (Danube main page); Dec 2025 (Danube FAQ) |
| Elitz 1, Elitz By Danube - 2 | 80.97%, whole project, 13 Aug 2026 | 31 Dec 2025 (passed) | Oct 2026 (Danube main page) |
| Elitz 2, Elitz 2 By Danube - 1 | 20.01%, whole project, 28 Sep 2026. Danube: 33%, 31 Aug 2026 | None on register | Dec 2027 (Danube main page); Q3 2026 (Danube FAQ) |
| Elitz 2, Elitz 2 By Danube - 2 | 20.01%, whole project, 28 Sep 2026 | None on register | Dec 2027 (Danube main page) |

Building names follow the DLD transaction register. The DLD gives one progress figure for each project, not each tower. Danube reports that concrete and blockwork are complete in both Elitz 1 towers.

## How the Elitz by Danube handover date has changed

| Date | What happened | Source |
|---|---|---|
| 22 Nov 2022 | Elitz 1 launched at Cityscape Dubai. | Khaleej Times |
| Dec 2022 | Elitz 1 sold out at launch, handover planned for Q4 2025. | Gulf News, 30 Dec 2022 |
| 1 May 2023 | Elitz 1 registered construction start. The register's completion date is 31 Dec 2025. | DLD register, via Mitchells |
| Mid 2023 | Elitz 2 launched, completion promised in Q3 2026. | Danube, release dated 9 Aug 2023 |
| 1 Nov 2023 | Elitz 2 registered construction start. No completion date filed. | DLD register, via Mitchells |
| 6 Jul 2026 | Elitz 1 at 72.42% at the DLD inspection. | DLD register, via Continental Club |
| 30 Jul 2026 | Elitz 1 named among 11 projects due within 12 months. | Danube, via Gulf News |
| 13 Aug 2026 | Elitz 1 at 80.97% at the DLD inspection. | DLD register, via Mitchells |
| 28 Sep 2026 | Elitz 2 at 20.01% at the DLD inspection, up from 16.82% on 30 Jun 2026. | DLD register, via Continental Club |
| 6 Oct 2026 | Danube pages show October 2026 for Elitz 1 and December 2027 for Elitz 2. | Danube |

## What the Elitz by Danube handover date means for payments

Both phases were sold on Danube's 1% monthly plan, with the balance due when the building is ready. In its Elitz 2 launch release Danube said buyers usually move in after paying about 60% of the price. A buyer keeps paying 1% a month until completion, so the delay at each phase means more of the price is paid in instalments and a smaller balance remains at handover. The exact split depends on each buyer's booking date and SPA.

## What to check before relying on the Elitz by Danube date

1. **Which Elitz phase the unit is in.** Elitz 1 and Elitz 2 are more than a year apart on Danube's own dates, and Elitz 3 is separate again.
2. **The SPA date and grace period for Elitz 1**, since its DLD registered date of 31 December 2025 has passed.
3. **Whether Elitz 2 has a completion date on the DLD register** for project 2693, through DLD's project status enquiry service.
4. **For Elitz 1, the civil defence and completion certificates**, the last steps Danube lists before handover.

## Frequently asked

### What is the Danube Elitz handover date?

Danube's project pages give October 2026 for Elitz 1 and December 2027 for Elitz 2 (accessed 6 Oct 2026). The FAQ sections on the same pages still show December 2025 and Q3 2026, the dates from launch.

### When will Elitz 1 be ready?

Danube shows October 2026. Its inspection of 31 August 2026 put Elitz 1 at 90%, with testing and commissioning and snagging under way and the civil defence inspection next. The DLD recorded 80.97% on 13 August 2026.

### When will Elitz 2 be ready?

Danube shows December 2027. The DLD recorded 20.01% on 28 September 2026, and Danube reported 33% on 31 August 2026, with the superstructure at the third podium level.

### Has the Danube Elitz handover date been delayed?

Yes. Elitz 1 launched in late 2022 for handover in Q4 2025 and now shows October 2026. Elitz 2 launched in 2023 for Q3 2026 and now shows December 2027, about 15 months later.

### Is Elitz 3 part of the same handover?

No. Elitz 3 is a separate DLD project with its own date. Danube gives April 2027 for it, and the DLD recorded 37.99% on 18 September 2026.

## Sources

- Mitchells Commercial Realty, Elitz By Danube DLD register, register as at 23 Sep 2026: https://www.mitchellscommercialrealty.com/off-plan/elitz-by-danube
- Mitchells Commercial Realty, Elitz 2 By Danube DLD register, register as at 23 Sep 2026: https://www.mitchellscommercialrealty.com/off-plan/elitz-2-by-danube
- Continental Club, Dubai project status (DLD register), updated 5 Oct 2026: https://continentalclub.ae/en/project-status/
- Continental Club, Elitz By Danube (DLD registry), registry updated 25 Sep 2026: https://continentalclub.ae/project/elitz-by-danube-jumeirah-village-circle/
- Danube Properties, Elitz project page, accessed 6 Oct 2026: https://danubeproperties.com/portfolio/elitz/
- Danube Properties, Elitz construction updates, 31 Aug 2026: https://danubeproperties.com/construction/elitz/
- Danube Properties, Elitz 2 project page, accessed 6 Oct 2026: https://danubeproperties.com/portfolio/elitz-2/
- Danube Properties, Elitz 2 construction updates, 31 Aug 2026: https://danubeproperties.com/construction/elitz-2/
- Khaleej Times, Danube launches Dh550 million Elitz at Cityscape Dubai, 22 Nov 2022: https://www.khaleejtimes.com/uae/dubai-soon-live-in-studio-apartment-with-private-pool-as-developer-launches-dh550-million-project
- Gulf News, Danube Properties' Dh550 million Elitz sold out on day of launch, 30 Dec 2022: https://gulfnews.com/business/corporate-news/danube-properties-dh550-million-elitz-sold-out-on-day-of-launch-1.1672396924899
- Danube Properties, Danube launches Dh900 million Elitz 2 in JVC, 9 Aug 2023: https://danubeproperties.com/high-demand-propels-danube-properties-to-launch-dh900-million-elitz-2-project-in-jvc-2/
- Gulf News, Danube Properties to deliver 11 Dubai projects in 12 months, 30 Jul 2026: https://gulfnews.com/gn-focus/company-news/danube-properties-to-deliver-11-dubai-projects-in-12-months-marking-major-milestone-1.500625819
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status