# When is the Elemental 22 handover date?

URL: https://www.dxbrealtor.ai/answers/elemental-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

The Elemental 22 handover date is 31 May 2028, the completion date held in the DLD project register, and the developer gives the same Q2 2028 target. A DLD inspection on 9 July 2026 recorded the building 25.86% complete, up from 15.22% in April 2026. The date has held since launch, but the date in each buyer's SPA, plus any grace period, is the one that applies.

## Key figures

- Registered completion date (DLD): 31 May 2028 (DLD project register via Continental Club)
- Latest construction progress: 25.86% (DLD inspection, 9 Jul 2026)
- Developer's stated date: Q2 2028 (Elemental Developments via Property Finder, accessed 11 Oct 2026)
- Change since launch: None (Q2 2028 at public release, 24 Apr 2025)

## Elemental 22 handover date: the latest position

Elemental 22 is due for completion on 31 May 2028, the date held in the DLD project register. Elemental Developments and Property Finder give the same target as Q2 2028. More on prices, sizes and the payment plan is on the [Elemental 22](/projects/elemental/) project page.

The latest DLD inspection, on 9 July 2026, recorded the building 25.86% complete. That was 10.64 points higher than the inspection on 9 April 2026 (DLD register via Continental Club, updated 4 October 2026). The 42 unit building is about 13 months into a three year build, and its progress so far fits the registered date.

## Elemental 22 handover date by building

Elemental 22 is a single building, so one date applies to every unit.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Elemental 22 (DLD project 3601) | 25.86%, 9 Jul 2026 | 31 May 2028 | Q2 2028 (developer, Property Finder) |

The registered building has a ground level, three parking levels and eight residential floors, with 13 one bedroom and 26 two bedroom apartments plus 3 other units.

## How the Elemental 22 handover date has changed

- **26 February 2025:** Hazza Zaal, CEO of Al Barari, launches Elemental Developments with Elemental 22 as its first project (Construction Week).
- **24 April 2025:** Public release after a sold out private VIP release, with handover marketed for Q2 2028 (Design Middle East; portals).
- **1 June 2025:** Construction start date in the DLD register.
- **September 2025:** The developer marks the groundbreaking (Elemental Developments, LinkedIn, 17 September 2025).
- **9 April 2026:** DLD inspection at 15.22%.
- **9 July 2026:** DLD inspection at 25.86%. The registered completion date remains 31 May 2028.

The date has not moved since launch. At the pace recorded between April and July 2026, about 3.5 points a month, the remaining 74 points would take about 21 months, which points to the second quarter of 2028.

The building sold out in its private VIP release before going on public sale in April 2025, and the most recent registered sale on Continental Club's list dates from 8 December 2025. Most owners therefore bought with the Q2 2028 date already in place, and no buyer has yet been offered a different one.

## What the Elemental 22 handover date means for payments

Continental Club, DirectDXB (4 October 2026) and OffplanIndex list a 60/40 plan: 5% down payment, 55% during construction and 40% on handover. Nothing is due after handover. On a 1 bedroom bought at about AED 1.75 million, that leaves about AED 700,000 to pay around May 2028. One portal, ezre, shows 20% on booking, 30% during construction and 50% on completion, so the share due on handover differs between sources.

## What to check before relying on the Elemental 22 date

1. **The completion date and grace period in the SPA.** Early buyers from the 2025 VIP release may hold contracts with different wording from later buyers.
2. **The handover instalment.** Confirm whether 40% or 50% is due on completion, and plan finance for that amount in 2028.
3. **The next DLD inspection.** The July 2026 figure is the latest; the DLD project status service shows newer inspections for project 3601 as they are recorded.

## Frequently asked

### When will Elemental 22 be completed?

The DLD project register gives a completion date of 31 May 2028. The building was 25.86% complete at the DLD inspection on 9 July 2026 (DLD register via Continental Club, updated 4 Oct 2026).

### Is Elemental 22 on schedule?

Progress rose from 15.22% on 9 April 2026 to 25.86% on 9 July 2026, about 3.5 points a month. At that pace the remaining work would take a little under two years, which is consistent with May 2028. No delay has been announced.

### Has the Elemental 22 handover date changed?

No. Portals listed Q2 2028 when the project went on public sale in April 2025, and the DLD register still shows 31 May 2028 in October 2026.

### How much is due at Elemental 22 handover?

Under the 60/40 plan listed by Continental Club and DirectDXB, 40% of the price is due on handover. One portal shows 50%, so the SPA schedule is the one to check.

## Sources

- Continental Club, Elemental 22 (DLD project register), registry updated 4 Oct 2026: https://continentalclub.ae/project/elemental-22-jumeirah-garden-city/
- Continental Club, Dubai handover 2028 tracker (DLD register, CC BY 4.0), accessed 11 Oct 2026: https://continentalclub.ae/handover-2028/
- Property Finder, Elemental 22 project page, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/elemental-developments/elemental-2
- Design Middle East, Elemental 22 public release, 24 Apr 2025: https://design-middleeast.com/elemental-22-sets-a-new-standard-for-inspired-urban-residences/
- Construction Week, Elemental 22 new real estate venture, 26 Feb 2025: https://www.constructionweekonline.com/news/elemental-22-al-barari
- Elemental Developments on LinkedIn, Elemental 22 groundbreaking, 17 Sep 2025: https://www.linkedin.com/posts/elemental-developments_elemental22-elementaldevelopments-jumeirahgardencity-activity-7373999928106373120-JEgk
- DirectDXB, Elemental 22 payment plan, 4 Oct 2026: https://www.directdxb.com/projects/elemental-elemental-22
- ezre, Elemental 22 payment plan, accessed 11 Oct 2026: https://ezre.ae/projects/elemental-22/payment-plan
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status