# When is the Eden House The Park handover date?

URL: https://www.dxbrealtor.ai/answers/eden-house-the-park-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Eden House The Park has a registered completion date of 25 February 2027, and the developer gives Q1 2027. The last Dubai Land Department inspection, on 30 July 2026, recorded the project 63.56% complete. All seven buildings sit under one registration, and Continental Club's estimate from the recent pace is a few months later, around June 2027.

## Key figures

- Registered completion date: 25 Feb 2027 (DLD project register via Continental Club)
- Latest construction progress: 63.56% (DLD inspection, 30 Jul 2026)
- Developer's stated date: Q1 2027 (Continental Club (developer supplied); Metropolitan; Inside Realty)
- Estimate at recent pace: About 9 Jun 2027 (Continental Club calculation, not a developer date)

## Eden House The Park handover date: the latest position

Eden House The Park is registered with the Dubai Land Department (DLD) for completion on 25 February 2027. At the last DLD inspection, on 30 July 2026, the project was 63.56% complete. Prices, sizes and the payment plan are on the project page: [Eden House The Park](/projects/eden-house-the-park/).

The developer's stated handover is Q1 2027, and Property Finder says handover is scheduled for 25 February 2027. All sources agree on the quarter. At the March to July 2026 pace, Continental Club estimates 100% around 9 June 2027, about three and a half months after the registered date.

## Eden House The Park handover date by building

The register lists the project as "Eden House The Park Building A" (DLD project 3382), but the registration covers seven low-rise buildings and 466 homes. Five of the buildings face the Dubai Water Canal.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Eden House The Park, all seven buildings (466 homes, registered as Building A) | 63.56% (30 Jul 2026) | 25 Feb 2027 | Q1 2027 (developer, via Continental Club; Metropolitan; Inside Realty); 25 Feb 2027 (Property Finder) |

No source publishes progress or a date for each building separately. The DLD figure is one reading for the whole registration.

## How the Eden House The Park handover date has changed

| Date | Event | Source |
|---|---|---|
| 7 Nov 2024 | Sales open and construction starts; completion registered for 25 Feb 2027 | Property Finder; DLD via Continental Club |
| 18 Nov 2024 | First DLD inspection | DLD via Continental Club |
| 30 Mar 2026 | DLD inspection: 43.13% | DLD via Continental Club |
| 30 Jul 2026 | DLD inspection: 63.56% | DLD via Continental Club |
| 2 Oct 2026 | Latest registered sale, a 2 bedroom at AED 6,391,492 | DLD via Continental Club |
| Oct 2026 | Register still shows 25 Feb 2027; developer gives Q1 2027 | Continental Club; Inside Realty |

The date has held since launch. The original schedule gave about 28 months from construction start. Between March and July 2026 the project gained 20.43 points, about five points a month. Finishing by 25 February 2027 would need about the same rate, roughly 36 points over seven months, through the finishing stage, which often runs slower than the structure.

## What the Eden House The Park handover date means for payments

Property Finder and Continental Club list 10% as a down payment, 30% in three instalments during construction and 60% on handover. Metropolitan lists 20% on booking, 20% during construction and 60% on handover. Either way, 60% of the price falls due at completion. On the 2 bedroom sold for AED 6,391,492 on 2 October 2026, that is about AED 3.8 million. If completion moves from February to around June 2027, that payment moves with it.

## What to check before relying on the Eden House The Park date

1. **The building named in the SPA.** Seven buildings share one registration, and the handover order between them is not published.
2. **The SPA completion date and grace period**, compared with the registered 25 February 2027.
3. **Mortgage approval timing for the 60% payment.** Bank offers usually carry an expiry date, and a slip of a few months could require a renewal.
4. **The next DLD inspection**, which will show whether the five-point monthly pace held after July 2026.

## Frequently asked

### Is Eden House The Park finished?

No. The DLD inspection of 30 July 2026 recorded the project 63.56% complete. Its registered completion date is 25 February 2027.

### What is the Eden House The Park completion date?

25 February 2027 on the DLD register (via Continental Club). Property Finder gives the same date and the developer gives Q1 2027.

### Has the Eden House The Park handover date been delayed?

No revised date has been filed. The registered date of 25 February 2027 has been in place since construction started in November 2024, and the developer still gives Q1 2027.

### Do all Eden House The Park buildings hand over together?

The DLD register holds one completion date for all seven buildings, registered as Eden House The Park Building A. No source publishes separate dates or progress for each building.

## Sources

- DLD project register via Continental Club, Eden House The Park Building A, inspection 30 Jul 2026; registry updated 7 Oct 2026: https://continentalclub.ae/project/eden-house-the-park-building-a-eden-house-the-park/
- DLD project register via Continental Club, handover 2027 list, accessed 11 Oct 2026: https://continentalclub.ae/handover-2027/
- Property Finder, Eden House The Park project page, accessed 11 Oct 2026: https://propertyfinder.ae/en/new-projects/handh-development-llc/eden-house-the-park
- Metropolitan Premium Properties, Eden House The Park, accessed 11 Oct 2026: https://metropolitan.realestate/jumeirah/eden-house-the-park/
- Inside Realty, H&H Development, accessed 11 Oct 2026: https://insiderealty.ae/en/real-estate-developers/h-h-development