# When is the DAMAC Casa handover date?

URL: https://www.dxbrealtor.ai/answers/damac-casa-handover-date/
Topic: Handover date
Updated: 2026-10-01

## Short answer

The DAMAC Casa handover date is Q2 2028, the project handover shown on DAMAC's own project page, while the unit listings on the same page show Q4 2028 (accessed 1 October 2026). The Dubai Land Department (DLD) inspection of 18 August 2026 put construction at 33.55% complete, up from 25.82% in April 2026. Sources reading the DLD register disagree on its completion date: Continental Club gives March 2028, PropertyStellar gives 30 May 2028, and Mitchells shows no completion date on file.

## Key figures

- Registered completion date (DLD): Mar to May 2028 (Continental Club (Mar 2028) and PropertyStellar (30 May 2028); Mitchells shows none on file)
- Latest construction progress: 33.55% (DLD inspection, 18 Aug 2026)
- Developer's stated date: Q2 2028 (DAMAC project page, accessed 1 Oct 2026. Unit listings show Q4 2028)
- Progress in four months: +7.73 points (25.82% on 21 Apr 2026 to 33.55% on 18 Aug 2026, DLD)

## DAMAC Casa handover date: the latest position

DAMAC Casa is due for handover in Q2 2028, the project handover date on DAMAC's own project page as accessed on 1 October 2026. The unit listings on the same page show Q4 2028, so DAMAC's own figures differ by two quarters. The Dubai Land Department inspection of 18 August 2026 recorded the tower 33.55% complete. Prices, sizes and the building itself are covered on the [DAMAC Casa](/projects/damac-casa/) page.

The DLD register does not settle the date. Continental Club, reading the register, gives completion in March 2028 and PropertyStellar gives 30 May 2028, while Mitchells' copy of the register, as at 15 June 2026, shows no completion date on file. Progress has been steady: 25.82% on 21 April 2026 and 33.55% on 18 August 2026, a gain of 7.73 points in four months. Finishing by 30 June 2028 would need the remaining 66.45% in about 22 months.

## DAMAC Casa handover date by building

DAMAC Casa is one tower, registered as DLD project 2801 under DAMAC's company Aqua Viridis Investment. One date and one progress figure apply to every unit.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| DAMAC Casa, 2 basements, ground, 2 podium and 42 residential floors (project 2801) | 33.55%, 18 Aug 2026 | March 2028 (Continental Club); 30 May 2028 (PropertyStellar); none on file (Mitchells) | Q2 2028 project handover, Q4 2028 on unit listings (DAMAC, 1 Oct 2026) |

The register counts 388 homes according to Mitchells and 405 according to Continental Club, while Propsearch estimates 379.

## How the DAMAC Casa handover date has changed

DAMAC launched the tower without a published handover date. Dates appeared later and all fall in 2028.

| Date | What happened | Source |
|---|---|---|
| 3 to 5 Oct 2023 | DAMAC launched DAMAC Casa from about AED 2.48 million, with no handover date in the launch coverage. | DAMAC; Gulf Business; Propsearch |
| 26 Dec 2023 | Construction start registered. | DLD register, via Mitchells |
| 21 Apr 2026 | 25.82% complete at DLD inspection. | DLD register, via Continental Club |
| 16 Jun 2026 | PropertyStellar listed handover as 30 May 2028. | PropertyStellar |
| 18 Aug 2026 | 33.55% complete at DLD inspection. | DLD register, via Continental Club and Mitchells |
| 1 Oct 2026 | DAMAC's page showed Q2 2028 for the project and Q4 2028 on unit listings. | DAMAC |

## What the DAMAC Casa handover date means for payments

The share due at handover depends on when the unit was bought. The launch plan was 24% on booking, 56% during construction and 20% on handover, according to Propsearch. Continental Club lists a 20/60/20 version. DAMAC's current project page lists a 24% deposit, 10 monthly instalments of 1% and 15 of 2% within 27 months of the sale date, and 40% on completion. These shares add to 104%, so the deposit appears to include the 4% DLD fee. On the current plan, a buyer pays 40% when the building completes, so a later handover moves the largest instalment later too.

## What to check before relying on the DAMAC Casa date

1. **Whether your SPA says Q2 2028, Q4 2028 or a specific day.** DAMAC's own page shows both quarters.
2. **Which payment plan your SPA follows**, since the handover share is 20% on the launch plan and 40% on the current one.
3. **The completion date DLD holds for project 2801**, through DLD's project status enquiry service, since sources reading the register disagree.
4. **The grace period in your SPA**, which applies if the date moves past the one your contract states.

## Frequently asked

### What is the DAMAC Casa completion date?

DAMAC's project page gives Q2 2028 for the project handover, while its unit listings show Q4 2028 (accessed 1 Oct 2026). Sources reading the DLD register give March 2028 (Continental Club) or 30 May 2028 (PropertyStellar), and Mitchells' copy of the register, as at 15 June 2026, shows no completion date on file.

### Is DAMAC Casa finished?

No. The DLD inspection of 18 August 2026 recorded the tower 33.55% complete. Construction started on 26 December 2023, according to the DLD register.

### When will DAMAC Casa be ready?

DAMAC gives Q2 2028. To finish by 30 June 2028, the remaining 66.45% would need to be built in about 22 months from the August 2026 inspection, faster than the 7.73 points recorded in the four months before it.

### Has the DAMAC Casa handover date been delayed?

No revised date has been announced. DAMAC's launch coverage in October 2023 gave no handover date, and the dates published in 2026 all fall in 2028, from March 2028 to DAMAC's own Q4 2028 on unit listings.

### How much is due at the DAMAC Casa handover?

It depends on when you bought. The launch plan was 24% on booking, 56% during construction and 20% on handover (Propsearch). DAMAC's current project page lists a 24% deposit, monthly instalments of 1% to 2% over 27 months, and 40% on completion (accessed 1 Oct 2026).

## Sources

- DAMAC Properties, DAMAC Casa project page, accessed 1 Oct 2026: https://www.damacproperties.com/en/projects/damac-casa
- DAMAC Properties, DAMAC Casa payment plan and launch date, accessed 1 Oct 2026: http://admin.damacproperties.com/en/damac-casa
- Continental Club, DAMAC Casa Dubai Media City (DLD registry data), registry updated 27 Sep 2026: https://continentalclub.ae/project/damac-casa-dubai-media-city/
- Mitchells Commercial Realty, DAMAC Casa DLD registry and registered sales, register as at 27 Sep 2026: https://www.mitchellscommercialrealty.com/off-plan/damac-casa
- PropertyStellar, DAMAC Casa, 16 Jun 2026: https://www.propertystellar.com/new-projects/dubai/damac-casa
- Propsearch, DAMAC Casa, updated 19 Aug 2026: https://propsearch.ae/dubai/damac-casa
- Gulf Business, DAMAC Casa to come up in Al Sufouh, island living at the heart of Dubai, 5 Oct 2023: https://gulfbusiness.com/damac-casa-to-come-up-in-al-sufouh-island-living-at-the-heart-of-dubai/
- The Skyscraper Center, DAMAC Casa, accessed 1 Oct 2026: https://www.skyscrapercenter.com/building/damac-casa/46529
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status