# When is the Burj Binghatti handover date?

URL: https://www.dxbrealtor.ai/answers/burj-binghatti-handover-date/
Topic: Handover date
Updated: 2026-10-06

## Short answer

Burj Binghatti Jacob and Co Residences has no current handover date from Binghatti. The registered completion date on the Dubai Land Department (DLD) register is 30 June 2026, the same June 2026 Binghatti gave in July 2025, and it has passed. The DLD site inspection of 31 August 2026 put the tower at 52.05% complete, and the Council on Tall Buildings and Urban Habitat now lists completion as 2027. Binghatti's own project page states no date.

## Key figures

- Registered completion date (DLD): 30 Jun 2026 (DLD register, via Mitchells and Continental Club, 30 Sep 2026. Date has passed)
- Latest construction progress: 52.05% (DLD site inspection, 31 Aug 2026)
- Developer's stated date: June 2026 (Binghatti blog, 23 Jul 2025. No later date on Binghatti's project page)
- Current estimate: 2027 (CTBUH Skyscraper Center, accessed 29 Sep 2026)

## Burj Binghatti handover date: the latest position

Burj Binghatti Jacob and Co Residences has no current handover date from Binghatti. The registered completion date on the Dubai Land Department (DLD) register is 30 June 2026, which matches the June 2026 completion Binghatti gave on its blog in July 2025. That date has passed without a handover, and Binghatti's own project page now states no date at all. Prices and sales records are on the [Burj Binghatti](/projects/burj-binghatti/) page.

The DLD site inspection of 31 August 2026 recorded the tower at 52.05% complete, up 17.49 points from 34.56% on 22 December 2025. The Council on Tall Buildings and Urban Habitat lists expected completion as 2027. At the pace recorded between the last two inspections, about 2.2 points a month, the remaining 47.95% would take around 22 months, though build rates on a tower change as work moves from structure to fit-out.

## Burj Binghatti handover date by building

Burj Binghatti is one tower, so one date and one progress figure apply to all units. The DLD register, project number 2480, lists 304 homes in one building; some trackers show other counts, including 325 and 671. The plot was first planned for Renaissance Tower, a 44 storey tower by Escan Real Estate that never went past the design stage and was cancelled, so that name carries no handover date of its own (Propsearch, updated 7 May 2025).

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Burj Binghatti Jacob and Co Residences (304 homes on the register) | 52.05%, 31 Aug 2026 | 30 Jun 2026 (passed) | Binghatti: none on project page. CTBUH: 2027 (29 Sep 2026) |

One broker, Cresco Real Estate, reports that a Binghatti listing gives 29 June 2027. That date does not appear on Binghatti's project page or in the DLD register.

## How the Burj Binghatti handover date has changed

| Date | What happened | Source |
|---|---|---|
| 1 Oct 2022 | DLD registered construction start. | DLD register, via Continental Club |
| 27 Nov 2022 | Tower announced as the world's tallest residential building. No completion date given. | The National |
| Jun 2023 | Sales launched, with an estimated handover of June 2026. | Propsearch |
| Feb 2025 | Above ground construction began, after enabling works. | Real Estate Club Dubai |
| 23 Jul 2025 | Binghatti says the tower will be completed by June 2026. | Binghatti blog |
| 22 Dec 2025 | 34.56% at the DLD site inspection. | DLD register, via Continental Club |
| 30 Jun 2026 | Registered completion date passes without a handover. | DLD register |
| 31 Aug 2026 | 52.05% at the DLD site inspection. | DLD register, via Mitchells |
| Sep 2026 | CTBUH lists expected completion as 2027. Binghatti's project page gives no date. | CTBUH; Binghatti |

## What the Burj Binghatti handover date means for payments

When the tower was announced, The National reported that buyers would pay 60% of the price during construction and the remaining 40% on handover (27 November 2022). On Binghatti's AED 13,999,999 launch price for its entry apartments, a 40% handover payment would be AED 5.6 million. Binghatti's current project page does not publish a plan, so later buyers may hold different terms. Under the launch structure, a later handover moves the date of the largest single payment.

## What to check before relying on the Burj Binghatti date

1. **The anticipated completion date and grace period in your SPA**, since the register still carries 30 June 2026 and Binghatti has published no replacement.
2. **The DLD progress for project 2480**, through DLD's project status enquiry service, to see whether the next inspection keeps the 2.2 points a month pace.
3. **Your payment schedule**, since the 60/40 launch terms put 40% at handover and later plans are not published.
4. **Written confirmation of any 2027 date** from Binghatti itself, since the June 2027 date reported by one broker is not on Binghatti's own page.

## Frequently asked

### What is the Burj Binghatti completion date?

The registered completion date on the DLD register is 30 June 2026 (project 2480), and it has passed without an update (Continental Club, registry updated 30 Sep 2026). The Council on Tall Buildings and Urban Habitat lists expected completion as 2027.

### Is Burj Binghatti finished?

No. The DLD site inspection of 31 August 2026 recorded the tower at 52.05% complete, up from 34.56% at the inspection of 22 December 2025.

### When will Burj Binghatti be ready?

Binghatti has not published a revised date. The Council on Tall Buildings and Urban Habitat lists 2027, and one broker, Cresco Real Estate, reports a Binghatti listing date of 29 June 2027, which Binghatti's own project page does not show.

### Has the Burj Binghatti handover date been delayed?

Yes. Binghatti's blog said in July 2025 that the tower would be completed by June 2026, and the DLD register still carries 30 June 2026. That date has passed with the tower just over half built.

### How much is due at the Burj Binghatti handover?

At the November 2022 announcement, buyers were to pay 60% during construction and 40% on handover (The National, 27 Nov 2022). Binghatti's current project page does not publish a payment plan.

### What is the Renaissance Tower handover date?

Renaissance Tower in Business Bay has no handover date because it was never built. Propsearch records it as a planned 44 storey mixed use tower by Escan Real Estate, first traced in May 2008, that did not move beyond the design stage and was cancelled (updated 7 May 2025). Burj Binghatti Jacob and Co Residences was later launched on the same plot.

## Sources

- Mitchell's, Burj Binghatti Jacob and Co Residences, DLD registry and sales (DLD project 2480), 31 Aug 2026: https://www.mitchellscommercialrealty.com/off-plan/burj-binghatti-jacob-co-residences
- Continental Club, Burj Binghatti Jacob and Co Residences (DLD register data), registry updated 30 Sep 2026: https://continentalclub.ae/project/burj-binghatti-jacob-co-residences-business-bay/
- Binghatti, Burj Binghatti, redefining luxury living in Dubai real estate (blog), 23 Jul 2025: https://www.binghatti.com/en/blog/burj-binghatti-impact-on-dubai-real-estate
- Binghatti, Burj Binghatti Jacob and Co Residences project page, accessed 1 Oct 2026: https://www.binghatti.com/en/branded-projects/burj-binghatti-jacob-co-residences
- The National, How Burj Binghatti is set to become the world's tallest residential tower, 27 Nov 2022: https://www.thenationalnews.com/uae/megaprojects/2022/11/27/how-burj-binghatti-is-set-to-become-the-worlds-tallest-residential-tower/
- Propsearch, Burj Binghatti Jacob and Co Residences, updated 28 Jul 2026: https://propsearch.ae/dubai/burj-binghatti-jacob-co-residences
- Propsearch, Renaissance Tower (cancelled, Business Bay), updated 7 May 2025: https://propsearch.ae/dubai/renaissance-tower
- CTBUH Skyscraper Center, Burj Binghatti Jacob and Co Residences, accessed 29 Sep 2026: https://www.skyscrapercenter.com/building/burj-binghatti-jacob-co-residences/45196/
- Real Estate Club Dubai, Burj Binghatti handover tracker, 17 Aug 2026: https://realestateclubdubai.com/handover-tracker/burj-binghatti-jacob-co-residences
- Cresco Real Estate, Burj Binghatti Jacob and Co, Business Bay, accessed 1 Oct 2026: https://crescorealestate.ae/property/burj-binghatti-jacob-and-co-residences-business-bay-dubai/
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status