# When is the Binghatti Titania handover date?

URL: https://www.dxbrealtor.ai/answers/binghatti-titania-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Binghatti Titania's registered completion date is 28 February 2027, and portals list Q1 2027 or February 2027, the date given at launch in October 2025. The only DLD inspection on record, on 23 September 2025, recorded 0%, a week before the registered construction start. No later progress figure had been published by 4 October 2026, so there is no official measure of how close the tower is to the February date.

## Key figures

- Registered completion date (DLD): 28 Feb 2027 (DLD register, project 4104)
- Latest construction progress: 0% (DLD inspection, 23 Sep 2025; no later figure)
- Developer's stated date: Q1 2027 (Developer supplied, via Continental Club)
- Date given at launch: February 2027 (Alnair, 13 Oct 2025)

## Binghatti Titania handover date: the latest position

Binghatti Titania's registered completion date on the DLD register is 28 February 2027. Continental Club lists the developer's date as Q1 2027, and Propsearch gives February 2027. Details of the Majan tower, its prices and payment plans are on the [Binghatti Titania](/projects/binghatti-titania/) page.

The register has published one inspection, on 23 September 2025, at 0%. That reading was taken before the registered construction start of 1 October 2025, and no newer one had appeared by 4 October 2026 (Mitchells). The register therefore gives no measure of progress during the first year of construction.

## Binghatti Titania handover date by building

Titania is a single tower under one DLD project number. Sources differ on its size.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Binghatti Titania (DLD project 4104; 789 or 614 units) | 0%, 23 Sep 2025 | 28 Feb 2027 | Q1 2027 (developer, via Continental Club); February 2027 (Propsearch, 31 Jan 2026); Q1 2027 (DirectDXB, 27 Sep 2026) |

Mitchells' copy of the register and Propsearch give 789 units, while Continental Club's copy gives 614. The building descriptions also differ: the register lists 25 residential floors, while Binghatti describes 32 residential floors in a 38 floor tower. Buyers have kept registering sales through 2026, with 721 recorded between June 2024 and 2 October 2026 (Mitchells), so a large number of owners depend on the same February 2027 date.

## How the Binghatti Titania handover date has changed

| Date | What was published | Source |
|---|---|---|
| 23 Sep 2025 | DLD inspection records 0% | DLD register via Continental Club |
| 1 Oct 2025 | Registered construction start | DLD register via Mitchells |
| 13 Oct 2025 | Launch in Majan, completion February 2027 | Alnair |
| 31 Jan 2026 | Estimated handover February 2027 | Propsearch |
| 27 Sep 2026 | Handover Q1 2027, sales continuing | DirectDXB |
| 4 Oct 2026 | Register still shows 28 February 2027 and 0% from September 2025 | DLD register via Mitchells |

The date has not moved since launch. The registered date allows 17 months from the registered construction start for a 38 storey tower, and without a newer inspection that timeline cannot be checked.

## What the Binghatti Titania handover date means for payments

Titania launched with a 50/50 plan. DirectDXB described it in September 2026 as 10% down, 40% during construction and 50% on handover. Agents also list a 70/30 plan with 30% on handover. On a studio at about AED 680,000, the handover payment is AED 340,000 on the 50/50 plan and AED 204,000 on the 70/30 plan. Buyers on the 50/50 plan carry half the price into the handover date, so any delay matters more to them.

## What to check before relying on the Binghatti Titania date

1. **A current progress figure.** The next DLD inspection for project 4104 will be the first official measure since September 2025.
2. **The SPA completion date and grace period**, against the registered 28 February 2027.
3. **Whether the contract is 50/50 or 70/30**, since the handover payment differs by 20% of the price.

## Frequently asked

### Is Binghatti Titania finished?

No. The DLD register lists it as under construction (Mitchells, 4 October 2026). Its only published inspection, on 23 September 2025, recorded 0%.

### What is the Binghatti Titania completion date?

The registered completion date on the DLD register is 28 February 2027. Binghatti's own project page did not show a date on 11 October 2026.

### Has the Binghatti Titania handover date been delayed?

No change has been published. The launch date of February 2027, Propsearch's estimate and the registered date of 28 February 2027 all agree. Without a newer DLD inspection, there is no official figure to test that date against.

### Why does the DLD register show 0% for Binghatti Titania?

The only inspection on the register took place on 23 September 2025, a week before the registered construction start of 1 October 2025. The register keeps that figure until DLD publishes a new inspection, so 0% reflects the date of the last inspection, not necessarily the site today.

## Sources

- DLD project register via Continental Club, Binghatti Titania, inspection 23 Sep 2025: https://continentalclub.ae/project/binghatti-titania-majan/
- DLD project register via Continental Club, handovers due in 2027, inspection 23 Sep 2025: https://continentalclub.ae/handover-2027/
- Mitchells Commercial Realty, Binghatti Titania DLD registry, 4 Oct 2026: https://www.mitchellscommercialrealty.com/off-plan/binghatti-titania
- Alnair, Binghatti Titania launches in Majan with 50/50 payment plan, 13 Oct 2025: https://alnair.ae/en/news/binghatti-titania-launches-in-majan-dubai-with-attractive-5050-payment-plan
- Propsearch, Binghatti Titania, updated 31 Jan 2026: https://propsearch.ae/dubai/binghatti-titania
- Binghatti, Binghatti Titania project page, accessed 11 Oct 2026: https://www.binghatti.com/en/projects/binghatti-titania
- DirectDXB, Titania by Binghatti Developers, 27 Sep 2026: https://www.directdxb.com/projects/binghatti-developers-titania-by-binghatti