## Short answer

The Binghatti Skyterraces handover date is 31 October 2027, the registered completion date on the DLD register, while broker listings citing the developer give December 2027. The only published DLD inspection, on 7 January 2026, recorded 0% complete, a week after the registered construction start. No later progress figure had been published by 11 October 2026, so the date cannot yet be checked against progress.

## Key figures

- Registered completion date (DLD): 31 Oct 2027 (DLD project 4327, via Continental Club and Dubai Handover)
- Latest construction progress: 0% (DLD inspection, 7 Jan 2026)
- Developer date in broker listings: Dec 2027 (Genz Properties, 2 Apr 2026)
- Latest portal date: Jan 2028 (Dubai Asset, 9 Oct 2026)

## Binghatti Skyterraces handover date: the latest position

Binghatti Skyterraces is due for completion on 31 October 2027. That is the registered completion date the Dubai Land Department holds for project 4327. Broker listings based on Binghatti's launch material give December 2027, two months later. More on prices and sizes is on the [Binghatti Skyterraces](/projects/binghatti-skyterraces/) page.

The DLD registered construction as starting on 1 January 2026, and its only published inspection, on 7 January 2026, recorded 0%. No newer figure had been added by 11 October 2026. One broker page updated on 9 October 2026 gives January 2028 (Dubai Asset), but neither Binghatti nor the DLD has changed the date.

## Binghatti Skyterraces handover date by building

Skyterraces is a single tower of 40 residential floors over six podium levels, so one date covers all units.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Binghatti Skyterraces (1,886 registered units) | 0%, 7 Jan 2026 | 31 Oct 2027 | Dec 2027 (Genz Properties); Jan 2028 (Dubai Asset) |

The unit total differs between republishers of the DLD register: 1,886 on Dubai Handover and Dubai Diligence, 1,587 on Continental Club. Binghatti's chief executive described 1,840 units in January 2026. On the 1,886 count, the mix is 643 studios, 1,050 one bedroom, 161 two bedroom and 6 three bedroom apartments, plus 26 shops. Buyer payments are held in an escrow account at Dubai Islamic Bank (DLD register, via Dubai Diligence).

## How the Binghatti Skyterraces handover date has changed

| Date | What happened | Source |
|---|---|---|
| Late 2025 | Launch in Motor City, Binghatti's first project there. Marketed for December 2027. | Muhammad Binghatti, LinkedIn, 5 Jan 2026; Genz Properties |
| 1 Jan 2026 | Construction start registered with the DLD. | DLD register, via Dubai Handover |
| 7 Jan 2026 | DLD inspection records 0%. Registered completion 31 October 2027. | DLD register, via Continental Club |
| 2 Apr 2026 | Broker listing still gives December 2027. | Genz Properties |
| 9 Oct 2026 | One broker page gives January 2028. | Dubai Asset |
| 11 Oct 2026 | DLD register still gives 31 October 2027, with no newer inspection published. | Dubai Handover; Continental Club |

## What the Binghatti Skyterraces handover date means for payments

Most listings give 20% on booking, 50% during construction and 30% on handover. The 30% handover payment is due when the tower is completed, whatever date that turns out to be. On a studio at the AED 774,999 launch price, it is AED 232,500. On a 1 bedroom at the AED 1,150,000 registered median, it is AED 345,000 (Dubai Diligence, October 2026).

## What to check before relying on the Binghatti Skyterraces date

1. **Which date the SPA uses**, 31 October 2027 or December 2027, and the grace period after it.
2. **The first DLD progress reading after January 2026**, through the DLD project status enquiry service for project 4327.
3. **How construction instalments are triggered in the SPA**, by dates or by progress milestones, since no progress has been published.

## Frequently asked

### What is the Binghatti Skyterraces completion date?

31 October 2027 on the DLD register for project 4327. Broker listings give December 2027 (Genz Properties, 2 April 2026).

### Has construction started at Binghatti Skyterraces?

The DLD registered construction as starting on 1 January 2026. The only published inspection, on 7 January 2026, recorded 0%, and no later figure was public by 11 October 2026.

### Has the Binghatti Skyterraces handover date been delayed?

Not on the DLD register, which still gives 31 October 2027. One broker page updated on 9 October 2026 gives January 2028 (Dubai Asset), but Binghatti has not announced a change.

### How much is due at the Binghatti Skyterraces handover?

30% of the price under the 20/50/30 plan most listings give. On a studio at the AED 774,999 launch price, that is AED 232,500.

## Sources

- Continental Club, Dubai handover 2027 tracker (DLD project register), inspection 7 Jan 2026; accessed 11 Oct 2026: https://continentalclub.ae/handover-2027/
- Dubai Handover, Binghatti Skyterraces (DLD project 4327), accessed 11 Oct 2026: https://dubaihandover.com/projects/4327-binghatti-skyterraces
- Dubai Diligence, Binghatti Skyterraces (DLD register), accessed 11 Oct 2026: https://dubaidiligence.com/projects/binghatti-skyterraces--p4327
- Binghatti, Binghatti SkyTerraces project page, accessed 11 Oct 2026: https://www.binghatti.com/en/projects/binghatti-skyterraces
- Muhammad Binghatti (Binghatti CEO), LinkedIn post on Binghatti Skyterraces, 5 Jan 2026: https://www.linkedin.com/posts/muhammad-binghatti-b4b158173_closing-off-2025-with-binghatti-skyterraces-activity-7413821027421511680-GRY4
- Genz Properties, Binghatti SkyTerraces, 2 Apr 2026: https://genz-properties.com/property/skyterraces/
- Dubai Asset, Binghatti Sky Terraces, 9 Oct 2026: https://dubaiasset.ae/en/projects/binghatti-sky-terraces
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status