# When is the Binghatti Skyhall handover date?

URL: https://www.dxbrealtor.ai/answers/binghatti-skyhall-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Binghatti Skyhall's registered completion date was 31 August 2026, and it has passed. Binghatti gives Q3 2026 and Property Finder 30 November 2026. The last DLD inspection, on 30 April 2026, recorded the tower 31.14% complete, with no newer figure published by 11 October 2026. No revised handover date has been announced, and the published dates do not match the progress recorded.

## Key figures

- Registered completion date (DLD): 31 Aug 2026 (Passed; DLD project 3504, via Continental Club and Dubai Handover)
- Latest construction progress: 31.14% (DLD inspection, 30 Apr 2026)
- Developer's stated date: Q3 2026 (Binghatti, accessed 11 Oct 2026)
- Portal date: 30 Nov 2026 (Property Finder, accessed 11 Oct 2026)

## Binghatti Skyhall handover date: the latest position

Binghatti Skyhall was registered for completion on 31 August 2026, and that date has passed. The last Dubai Land Department inspection, on 30 April 2026, recorded the tower 31.14% complete, four months before the registered date. More on prices and sizes is on the [Binghatti Skyhall](/projects/binghatti-skyhall/) page.

The published targets still sit in 2026. Binghatti's page says Q3 2026, which has ended, and Property Finder lists 30 November 2026. Propsearch and Continental Club give Q4 2026. No newer DLD inspection and no revised date had been published by 11 October 2026.

## Binghatti Skyhall handover date by building

Skyhall is one tower with 728 units, so a single date and progress figure apply.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Binghatti Skyhall (489 studios, 228 1 bedrooms, 11 shops) | 31.14%, 30 Apr 2026 | 31 Aug 2026 (passed) | Q3 2026 (Binghatti); 30 Nov 2026 (Property Finder); Q4 2026 (Propsearch) |

## How the Binghatti Skyhall handover date has changed

| Date | What happened | Source |
|---|---|---|
| 16 Jan 2025 | First DLD inspection on record. | DLD register, via Continental Club |
| 1 Feb 2025 | Booking opened and the DLD registered construction start. | Property Finder; DLD register |
| Apr 2025 | Public launch reported. | Metropolitan Premium Properties, 22 Apr 2025 |
| 30 Apr 2026 | DLD inspection records 31.14% complete. | DLD register, via Continental Club |
| 28 Jul 2026 | Propsearch still estimates Q4 2026. | Propsearch |
| 31 Aug 2026 | Registered completion date passes. | DLD register |
| 11 Oct 2026 | Binghatti still says Q3 2026; Property Finder says 30 November 2026. No new DLD inspection published. | Binghatti; Property Finder |

Property Finder and Propsearch give Q4 2026, the DLD register holds an earlier 31 August 2026, and Binghatti's FAQ says Q3 2026. None of these has been updated for the April 2026 progress figure.

## What the Binghatti Skyhall handover date means for payments

The plan is 20% on booking, 50% during construction and 30% on completion. The 30% falls due when the building is completed, so a later completion delays it. On a studio at the AED 975,000 launch price, the completion payment is AED 292,500. On a 838 sq ft 1 bedroom bought at AED 1,904,000 in September 2026, it would be AED 571,200 (Continental Club, DLD data).

## What to check before relying on the Binghatti Skyhall date

1. **The completion date and grace period in the SPA**, since the three published dates differ and the registered one has passed.
2. **Whether the DLD has recorded an extension for project 3504**, through the DLD project status enquiry service.
3. **The next DLD inspection figure.** The April 2026 reading is the last one public, so current progress is unknown.
4. **The completion notice terms in the SPA**, which set how much warning is given before the 30% payment.

## Frequently asked

### Is Binghatti Skyhall finished?

No. The DLD recorded it 31.14% complete at its inspection on 30 April 2026, the latest published figure.

### What is the Binghatti Skyhall completion date?

31 August 2026 on the DLD register for project 3504. Binghatti's page gives Q3 2026, and Property Finder gives an expected completion of 30 November 2026.

### Has the Binghatti Skyhall handover date been delayed?

The registered date passed on 31 August 2026 with the tower about a third built, so handover will be later than registered. Binghatti had not published a new date by 11 October 2026.

### How much is due at the Binghatti Skyhall handover?

30% of the price under the 20/50/30 plan. On a studio at the AED 975,000 launch price, that is AED 292,500.

## Sources

- Continental Club, Binghatti Skyhall (DLD registry), inspection 30 Apr 2026; accessed 11 Oct 2026: https://continentalclub.ae/project/binghatti-skyhall-business-bay/
- Continental Club, Dubai handover 2026 tracker (DLD project register), accessed 11 Oct 2026: https://continentalclub.ae/handover-2026/
- Dubai Handover, Binghatti Skyhall (DLD project 3504), accessed 11 Oct 2026: https://dubaihandover.com/projects/3504-binghatti-skyhall
- Binghatti, Binghatti Skyhall project page, accessed 11 Oct 2026: https://www.binghatti.com/en/projects/binghatti-skyhall
- Property Finder, Binghatti Skyhall project page, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/binghatti-developers/binghatti-skyhall
- Propsearch, Binghatti Skyhall, updated 28 Jul 2026: https://propsearch.ae/dubai/binghatti-skyhall
- Metropolitan Premium Properties, Binghatti Skyhall, a new project in Business Bay, 22 Apr 2025: https://metropolitan.realestate/media/news/binghatti-skyhall-a-new-project-in-business-bay/
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status
