# When is the Binghatti Skyflame handover date?

URL: https://www.dxbrealtor.ai/answers/binghatti-skyflame-handover-date/
Topic: Handover date
Updated: 2026-10-01

## Short answer

The Binghatti Skyflame handover date is 31 December 2027, the registered completion date on the Dubai Land Department (DLD) register and the date Binghatti gives on its own project page. The DLD site inspection of 17 February 2026 recorded construction at 0%, and no later inspection had been published by 1 October 2026. Skyflame 2, sold alongside it in the same Majan scheme, is registered separately with the same 31 December 2027 date.

## Key figures

- Registered completion date (DLD): 31 Dec 2027 (DLD register, project 4393, via Continental Club, 30 Sep 2026)
- Latest construction progress: 0% (DLD site inspection, 17 Feb 2026, the only one published)
- Developer's stated date: 31 Dec 2027 (Binghatti, accessed 1 Oct 2026)
- Date change since launch: None recorded (Property Finder; Dubai Handover daily register snapshots to 1 Oct 2026)

## Binghatti Skyflame handover date: the latest position

Binghatti Skyflame is due for completion on 31 December 2027. Binghatti gives that date on its own project page, and the Dubai Land Department register holds the same registered completion date for project number 4393. The only DLD site inspection published so far, on 17 February 2026, recorded 0% complete. Prices, the payment plan and sales are covered on the [Binghatti Skyflame](/projects/binghatti-skyflame/) page.

The register lists a construction start of 1 February 2026, so the February inspection came about two weeks into the build. No later inspection had been published by 1 October 2026 (Dubai Handover, DLD data). To meet 31 December 2027, two towers of 27 and 22 residential floors, each on five parking levels, would be built in about 22 months from that first inspection.

## Binghatti Skyflame handover date by building

Project 4393 covers both Skyflame towers and 1,407 units, with one progress figure and one date. Skyflame 2, in the same Majan scheme, is a separate DLD project.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Skyflame Tower 1 (G + 5 parking + 27 residential floors, 29 shops) | 0%, project 4393, 17 Feb 2026 | 31 Dec 2027 | 31 Dec 2027 (Binghatti); Dec 2027 (Property Finder) |
| Skyflame Tower 2 (G + 5 parking + 22 residential floors, 19 shops) | 0%, project 4393, 17 Feb 2026 | 31 Dec 2027 | 31 Dec 2027 (Binghatti); Dec 2027 (Property Finder) |
| Skyflame 2 (801 units, separate project 4399) | 0%, 16 Feb 2026 | 31 Dec 2027 | Q4 2027 (developer, via Continental Club) |

Floor counts are from Binghatti and the developer's filed description on the DLD register. Propsearch describes Skyflame 1 as a single 34 storey building with 1,406 units, which differs from the register's two tower description.

## How the Binghatti Skyflame handover date has changed

The date has not moved since sales opened.

| Date | What happened | Source |
|---|---|---|
| 1 Feb 2026 | Booking opened and the DLD registered the construction start. Expected completion 31 December 2027. | Property Finder; DLD register |
| 16 and 17 Feb 2026 | First DLD inspections: Skyflame 2 at 0% and Skyflame at 0%. | DLD register, via Continental Club |
| 30 Sep 2026 | 768 sales registered at Skyflame since launch; no new inspection published. | DLD register, via Continental Club |
| 1 Oct 2026 | Register still shows 0% and 31 December 2027. | Dubai Handover, DLD snapshots |

## What the Binghatti Skyflame handover date means for payments

Binghatti's plan is 20% at booking, 50% during construction and 30% on completion. The DLD register records a median sale price of AED 550,000 for a studio and AED 1.1 million for a 1 bedroom (Continental Club, 30 September 2026). On those prices, AED 165,000 or AED 330,000 falls due at completion. If completion moves later than 31 December 2027, the 30% payment moves with it.

## What to check before relying on the Binghatti Skyflame date

1. **Whether your unit is in Skyflame (project 4393) or Skyflame 2 (project 4399).** Both carry 31 December 2027 today, but each has its own register entry, inspections and escrow account.
2. **The completion date and grace period in your SPA**, since the register date is a filed date, not a delivery promise.
3. **Whether a second DLD inspection has been published.** By 1 October 2026 the only figure was 0% from February 2026, so the next reading will be the first sign of build pace.
4. **How the 50% construction share is scheduled in your SPA**, since that share falls due before the 30% completion payment.

## Frequently asked

### What is the Binghatti Skyflame completion date?

31 December 2027. Binghatti's project page states it, and the DLD register holds the same registered completion date for project number 4393. Property Finder lists December 2027 (all accessed 1 Oct 2026).

### Is Binghatti Skyflame finished?

No. Booking and construction started in early February 2026, and the DLD site inspection of 17 February 2026 recorded 0% complete. No later DLD figure had been published by 1 October 2026 (Dubai Handover, DLD data).

### Has the Binghatti Skyflame handover date been delayed?

No change has been recorded. The date has been 31 December 2027 since booking opened on 1 February 2026, and the register still showed it on 1 October 2026 (Property Finder; Dubai Handover).

### When will Binghatti Skyflame 2 be ready?

Skyflame 2 is a separate DLD project, number 4399, with 801 units. Its registered completion date is also 31 December 2027, and its DLD inspection of 16 February 2026 recorded 0% (Continental Club, DLD data, 26 Sep 2026).

### How much is due at the Binghatti Skyflame handover?

30% of the price. Binghatti's plan is 20% at booking, 50% during construction and 30% on completion. On the AED 1.1 million median 1 bedroom sale price, that is AED 330,000 (Continental Club, DLD data, 30 Sep 2026).

## Sources

- Binghatti, Binghatti Skyflame, accessed 1 Oct 2026: https://www.binghatti.com/en/projects/binghatti-skyflame
- Continental Club, Binghatti Skyflame (DLD registry), registry updated 30 Sep 2026: https://continentalclub.ae/project/binghatti-skyflame-majan/
- Continental Club, Binghatti Skyflame 2 (DLD registry), registry updated 26 Sep 2026: https://continentalclub.ae/project/binghatti-skyflame-2-majan/
- Dubai Handover, Binghatti Skyflame 1 (DLD snapshots), snapshot 1 Oct 2026: https://dubaihandover.com/projects/4393-binghatti-skyflame
- Property Finder, Binghatti Skyflame project page, accessed 1 Oct 2026: https://www.propertyfinder.ae/en/new-projects/binghatti-developers/binghatti-skyflame
- Propsearch, Binghatti Skyflame 1, updated 23 Apr 2026: https://propsearch.ae/dubai/binghatti-skyflame-1
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status