# When is the Binghatti Skyblade handover date?

URL: https://www.dxbrealtor.ai/answers/binghatti-skyblade-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Binghatti Skyblade's registered completion date is 30 November 2027, and Binghatti gives Q4 2027. The DLD inspection on 21 April 2026 recorded the tower 17.06% complete, up from 6.02% on 20 August 2025. The date has not changed since the September 2025 launch, but with more than four fifths of the work left at the last inspection, buyers rely on the SPA date and its grace period.

## Key figures

- Registered completion date (DLD): 30 Nov 2027 (DLD register, project 3725)
- Latest construction progress: 17.06% (DLD inspection, 21 Apr 2026)
- Developer's stated date: Q4 2027 (Binghatti, accessed 11 Oct 2026)
- Progress since August 2025: +11.04 points (6.02% on 20 Aug 2025 to 17.06% on 21 Apr 2026)

## Binghatti Skyblade handover date: the latest position

Binghatti Skyblade is due for completion in Q4 2027. The DLD register holds a registered completion date of 30 November 2027 for the Downtown Dubai tower, and Binghatti's own page gives Q4 2027. Prices and the payment plan are on the [Binghatti Skyblade](/projects/binghatti-skyblade/) page.

The latest DLD inspection, on 21 April 2026, recorded 17.06% complete. That was about 19 months before the registered date. No newer inspection had been published by 4 October 2026.

## Binghatti Skyblade handover date by building

Skyblade is a single tower, filed on the DLD register as one building with 596 units.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Binghatti Skyblade (DLD project 3725, 596 units) | 17.06%, 21 Apr 2026 | 30 Nov 2027 | Q4 2027 (Binghatti); Q4 2027 (Propsearch, 14 Aug 2026); November 2027 (Data Habibi) |

## How the Binghatti Skyblade handover date has changed

| Date | What was published | Source |
|---|---|---|
| 1 Feb 2025 | Registered construction start | DLD register via Mitchells |
| 20 Aug 2025 | 6.02% complete at DLD inspection | DLD register via Continental Club |
| Sep 2025 | Launch in Istanbul as an AED 2 billion, 621 residence tower | Construction Week Online |
| 21 Apr 2026 | 17.06% complete at DLD inspection | DLD register via Continental Club |
| 14 Aug 2026 | Estimated handover Q4 2027 | Propsearch |
| 4 Oct 2026 | Register still shows 30 November 2027 | DLD register via Mitchells |

The date has held at Q4 2027 since launch. Progress between the two published inspections averaged a little under 1.4 points a month.

To reach 100% by 30 November 2027, the tower needs about 83 more points in roughly 19 months from the April 2026 inspection, close to 4.4 points a month. That is about three times the rate recorded between August 2025 and April 2026. The next published inspection will show whether the pace has picked up.

## What the Binghatti Skyblade handover date means for payments

Binghatti's current plan puts 30% of the price on completion. Propsearch and Data Habibi record the launch plan with 40% on handover. For a 2 bedroom bought at AED 4,959,999, the October 2026 registered price, the completion payment is about AED 1.49 million under the 30% plan and about AED 1.98 million under the 40% plan. That payment moves with the handover date.

## What to check before relying on the Binghatti Skyblade date

1. **The completion date and grace period in the SPA**, compared with the registered 30 November 2027.
2. **The next DLD inspection for project 3725**, since the last published figure is from April 2026.
3. **Whether the contract is on the 30% or 40% handover plan**, which changes the size of the final payment.

## Frequently asked

### Is Binghatti Skyblade finished?

No. It was 17.06% complete at the DLD inspection on 21 April 2026, and the register lists it as under construction (Mitchells, 4 October 2026).

### What is the Binghatti Skyblade completion date?

The registered completion date on the DLD register is 30 November 2027. Binghatti gives Q4 2027.

### Has the Binghatti Skyblade handover date been delayed?

No change has been published. Binghatti, Propsearch and Data Habibi all give Q4 2027, matching the registered date of 30 November 2027.

### How many units does Binghatti Skyblade have?

The DLD register lists 596 units in one building. Binghatti lists 619 homes and 2 shops, and announced 621 residences at the September 2025 launch.

## Sources

- DLD project register via Continental Club, Binghatti Skyblade, inspection 21 Apr 2026: https://continentalclub.ae/project/binghatti-skyblade-downtown-dubai/
- DLD project register via Continental Club, handovers due in 2027, inspection 21 Apr 2026: https://continentalclub.ae/handover-2027/
- Mitchells Commercial Realty, Binghatti Skyblade DLD registry, 4 Oct 2026: https://www.mitchellscommercialrealty.com/off-plan/binghatti-skyblade
- Binghatti, Binghatti Skyblade project page, accessed 11 Oct 2026: https://www.binghatti.com/en/projects/binghatti-skyblade
- Propsearch, Binghatti Skyblade, updated 14 Aug 2026: https://propsearch.ae/dubai/binghatti-skyblade
- Data Habibi, Binghatti Skyblade, accessed 11 Oct 2026: https://datahabibi.ae/dubai/new-projects/binghatti-skyblade
- Construction Week Online, Binghatti launches AED2bn Dubai project Skyblade in Istanbul, 9 Sep 2025: https://www.constructionweekonline.com/projects-tenders/binghatti-skyblade-istanbul