# When is the Binghatti Ruby handover date?

URL: https://www.dxbrealtor.ai/answers/binghatti-ruby-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Binghatti Ruby's registered completion date is 28 February 2026, and Binghatti still gives Q1 2026, but the tower has not been handed over. The latest DLD inspection, on 23 July 2026, recorded it 46.43% complete. Propsearch now estimates handover in Q4 2027, so the published date is no longer a guide to when keys will be ready.

## Key figures

- Registered completion date (DLD): 28 Feb 2026 (DLD project register via Continental Club)
- Latest construction progress: 46.43% (DLD inspection, 23 Jul 2026)
- Developer's stated date: Q1 2026 (Binghatti project page, accessed 11 Oct 2026)
- Portal estimate: Q4 2027 (Propsearch, updated 15 Aug 2026)

## Binghatti Ruby handover date: the latest position

Binghatti Ruby has a registered completion date of 28 February 2026 in the DLD project register, and Binghatti's own page still says Q1 2026. That date has passed and the tower is not finished. More detail on prices and the building is on the [Binghatti Ruby](/projects/binghatti-ruby/) page.

At the latest DLD inspection, on 23 July 2026, the building was 46.43% complete. Propsearch, updated on 15 August 2026, puts the estimated handover at Q4 2027. Binghatti has not announced a revised date.

## Binghatti Ruby handover date by building

Binghatti Ruby is one tower, registered with DLD as a single project (project number 3533) with 628 units.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Binghatti Ruby | 46.43%, 23 Jul 2026 | 28 Feb 2026 | Q1 2026 (Binghatti); Q4 2027 estimate (Propsearch, 15 Aug 2026) |

## How the Binghatti Ruby handover date has changed

| Date | What happened | Source |
|---|---|---|
| 13 Dec 2024 | Binghatti facts sheet issued at launch, studios from AED 695,000 | Binghatti via Mitchells |
| 17 Dec 2024 | Listing gives a Q4 2025 completion date | Arab Property |
| 1 Jan 2025 | Construction start recorded | DLD register |
| 28 Feb 2026 | Registered completion date passes | DLD register |
| 10 Mar 2026 | Inspection records 20.04% complete | DLD register |
| 23 Jul 2026 | Inspection records 46.43% complete | DLD register |
| 15 Aug 2026 | Estimated handover given as Q4 2027 | Propsearch |

The registered date and the developer's date have not moved, even though the building has fallen well behind them. The Q4 2025 figure from the launch listing does not match Binghatti's Q1 2026, so the launch promise depends on the source.

## What the Binghatti Ruby handover date means for payments

Binghatti's plan is 20% on booking, 50% during construction and 30% on completion. The final 30% is tied to completion, not to a calendar date, so it falls due only when the building is finished. On a studio bought at the launch price of AED 695,000, that last payment would be about AED 208,500. No post-handover plan is listed for this project.

## What to check before relying on the Binghatti Ruby date

1. **The completion date and grace period in your SPA.** The SPA date, not the Q1 2026 marketing date, is what the contract enforces.
2. **Which construction instalments are tied to progress.** The SPA sets which parts of the 50% construction share follow building milestones, which matters since the tower was only 46.43% complete in July 2026.
3. **The next DLD inspection.** DLD's project status service publishes new figures after each inspection; the July 2026 figure is the latest available.
4. **Resale timing.** Only one of 604 registered sales was a resale, so anyone planning to sell before completion has little price history to go on.

## Frequently asked

### Is Binghatti Ruby finished?

No. The DLD register recorded the tower 46.43% complete at its inspection on 23 July 2026. It has not been handed over.

### What is the Binghatti Ruby completion date?

The DLD project register holds a completion date of 28 February 2026, and Binghatti's project page gives Q1 2026. Both have passed. Propsearch estimated Q4 2027 when it updated its page on 15 August 2026.

### Has the Binghatti Ruby handover date been delayed?

In practice, yes. Arab Property listed a Q4 2025 completion date at launch in December 2024, and Binghatti listed Q1 2026. The building was less than half built in July 2026. Binghatti has not published a new date.

### How fast is construction moving at Binghatti Ruby?

Progress rose from 20.04% on 10 March 2026 to 46.43% on 23 July 2026, a gain of 26.39 points in about four and a half months (DLD project register via Continental Club).

## Sources

- DLD project register via Continental Club, Binghatti Ruby, inspection 23 Jul 2026, register updated 4 Oct 2026: https://continentalclub.ae/project/binghatti-ruby-jvc-district-16/
- DLD project register via Continental Club, Dubai handover 2026 tracker, accessed 11 Oct 2026: https://continentalclub.ae/handover-2026/
- Binghatti, Binghatti Ruby project page, accessed 11 Oct 2026: https://www.binghatti.com/en/projects/binghatti-ruby
- Propsearch, Binghatti Ruby, updated 15 Aug 2026: https://propsearch.ae/dubai/binghatti-ruby
- Arab Property, Ruby by Binghatti, 17 Dec 2024: https://arabproperty.com/houses/binghatti-ruby-in-jvc/
- Mitchells, Binghatti Ruby project brief (Binghatti facts sheet, Dec 2024), accessed 11 Oct 2026: https://www.mitchellscommercialrealty.com/projects/binghatti-ruby
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status