# When is the Binghatti Luxuria handover date?

URL: https://www.dxbrealtor.ai/answers/binghatti-luxuria-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

The Binghatti Luxuria handover date is 30 July 2027, the registered completion date on the Dubai Land Department (DLD) register, and Binghatti gives Q3 2027. The DLD inspection of 17 September 2026 recorded the tower 7.04% complete, about nine months after the registered start of 1 January 2026. The date has not moved, but 93% of the work remained with about ten months to go.

## Key figures

- Registered completion date (DLD): 30 Jul 2027 (DLD project register via Continental Club)
- Latest construction progress: 7.04% (DLD inspection, 17 Sep 2026)
- Developer's stated date: Q3 2027 (Binghatti, accessed 11 Oct 2026)
- Portal date: 30 Jul 2027 (Property Finder, accessed 11 Oct 2026)

## Binghatti Luxuria handover date: the latest position

Binghatti Luxuria is due for completion on 30 July 2027. That is the registered completion date on the Dubai Land Department (DLD) register. Binghatti's project page says Q3 2027, and Property Finder lists the same 30 July 2027. More on prices and sizes is on the [Binghatti Luxuria](/projects/binghatti-luxuria/) page.

The DLD inspection of 17 September 2026 recorded the tower 7.04% complete. Work was registered as starting on 1 January 2026. Dubai Handover, which compares the DLD record against the calendar each day, projects a finish well after July 2027 if the pace seen so far continues. That is a projection, not a revised date.

## Binghatti Luxuria handover date by building

Binghatti Luxuria is a single tower in Jumeirah Village Triangle (JVT), with 469 units on the DLD project record.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Binghatti Luxuria (one tower, 33 floors, 469 units) | 7.04%, 17 Sep 2026 | 30 Jul 2027 | Q3 2027 (Binghatti); 30 Jul 2027 (Property Finder) |

## How the Binghatti Luxuria handover date has changed

The published date has not moved since launch. What has changed is the time left to meet it.

| Date | What happened | Source |
|---|---|---|
| 1 Jan 2026 | Registered construction start. | DLD record via Dubai Handover |
| 19 Feb 2026 | First sales registered with the DLD. | Dubai Handover |
| 17 Mar 2026 | Portals list handover in July 2027 and studios from AED 765,999. | Dubai Asset |
| 17 Sep 2026 | DLD inspection records 7.04% complete. | DLD register via Continental Club |
| Oct 2026 | Binghatti still gives Q3 2027; the register still shows 30 July 2027. | Binghatti; Dubai Handover |

## What the Binghatti Luxuria handover date means for payments

Binghatti's plan is 20% on booking, 50% during construction and 30% on completion. Excel Properties lists the construction share as 3% a month for 16 months plus one 2% instalment. Monthly instalments run on dates, not on build stages. A buyer who booked in February 2026 would have paid most of the 50% by mid 2027, whether or not the tower is near completion.

The 30% completion payment is about AED 235,000 on a studio at the median registered price of AED 782,499, and about AED 390,000 on a 1 bedroom at about AED 1.3 million (DLD sales via Dubai Handover, accessed 11 October 2026).

## What to check before relying on the Binghatti Luxuria date

1. **The completion date and grace period written in the SPA.** The register date of 30 July 2027 is ambitious for a tower at 7% in September 2026.
2. **Whether instalments are monthly or tied to progress.** Under a monthly schedule, the 50% construction share is not linked to how far the tower has risen.
3. **The next DLD inspections.** Progress between now and early 2027 will show whether the July 2027 date holds.
4. **Binghatti's record on recent towers.** Several of its projects due in 2026 have passed their published dates, as the [Binghatti handover date tracker](/answers/binghatti-handover-dates/) shows.

## Frequently asked

### What is the Binghatti Luxuria completion date?

30 July 2027 on the DLD register. Binghatti gives Q3 2027 and Property Finder lists 30 July 2027 (accessed 11 Oct 2026).

### Is Binghatti Luxuria finished?

No. The DLD inspection of 17 September 2026 recorded 7.04% complete. Construction was registered as starting on 1 January 2026.

### Has the Binghatti Luxuria handover date been delayed?

Not on paper. Dubai Handover's daily copy of the DLD record shows 30 July 2027 unchanged, and Binghatti and portals have listed July 2027 or Q3 2027 since at least March 2026. Progress of 7.04% in September 2026 leaves a short window to meet it.

### How much is due at the Binghatti Luxuria handover?

30% of the price, under Binghatti's 20/50/30 plan. On a studio at the median registered price of AED 782,499, that is about AED 235,000.

## Sources

- DLD project register via Continental Club, inspection 17 Sep 2026, inspection 17 Sep 2026: https://continentalclub.ae/handover-2027/
- Binghatti Developers, Binghatti Luxuria, accessed 11 Oct 2026: https://www.binghatti.com/en/projects/binghatti-luxuria
- Property Finder, Binghatti Luxuria project page, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/binghatti-developers/binghatti-luxuria
- Dubai Handover, Binghatti Luxuria (DLD record history and sales), accessed 11 Oct 2026: https://dubaihandover.com/projects/4299-binghatti-luxuria
- Dubai Asset, Binghatti Luxuria, 17 Mar 2026: https://dubaiasset.ae/en/projects/binghatti-luxuria
- Excel Properties, Binghatti Luxuria payment plan, accessed 11 Oct 2026: https://excelproperties.ae/offplan/binghatti-luxuria-jvt
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status