# When is the Binghatti Cullinan handover date?

URL: https://www.dxbrealtor.ai/answers/binghatti-cullinan-handover-date/
Topic: Handover date
Updated: 2026-10-01

## Short answer

The registered completion date for Binghatti Cullinan is 30 June 2027, the same date given in launch materials in November 2025 (DLD register via Continental Club, updated 29 September 2026). The only DLD inspection published so far, on 25 November 2025, recorded 0% complete, before the registered construction start of 1 December 2025, and no later inspection had been posted by 1 October 2026. Binghatti's own project page gives no date, and portal dates run later, with Propsearch estimating Q4 2027.

## Key figures

- Registered completion date (DLD): 30 Jun 2027 (DLD project 4247, via Continental Club, updated 29 Sep 2026)
- Latest construction progress: 0% (DLD inspection, 25 Nov 2025. No later inspection published)
- Developer's stated date: Not on Binghatti's page (Binghatti, accessed 1 Oct 2026. Q2 2027 listed as developer supplied by Continental Club)
- Portal estimate: Q4 2027 (Propsearch, updated 6 Aug 2026)

## Binghatti Cullinan handover date: the latest position

The registered completion date for Binghatti Cullinan, a single tower in Al Jaddaf, is 30 June 2027, according to the Dubai Land Department register as republished by Continental Club on 29 September 2026. The same date appeared in launch materials when units were released on 20 November 2025. Binghatti's own project page gives no completion date. Prices, sizes and sales figures are on the [Binghatti Cullinan](/projects/binghatti-cullinan/) page.

The only DLD inspection published so far, on 25 November 2025, recorded 0% complete, a week before the registered construction start of 1 December 2025. No later inspection had been posted by 1 October 2026, so there is no official progress figure for 2026. Portals are split between Q2 2027 and Q4 2027.

## Binghatti Cullinan handover date by building

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Binghatti Cullinan, DLD project 4247 (1 tower, B+G+4P+14) | 0%, 25 Nov 2025 | 30 Jun 2027 (Continental Club); not filed (Mitchells) | Q2 2027 (Data Habibi; developer supplied per Continental Club); Q4 2027 (Propsearch) |

The two copies of the register disagree on the completion date: Continental Club's, updated 29 September 2026, shows 30 June 2027, while Mitchells Commercial Realty's, dated 15 June 2026, shows none on file. Unit counts also vary, from 630 (Continental Club) to 643 (Mitchells) and about 645 (Propsearch).

## How the Binghatti Cullinan handover date has changed

| Date | What happened | Source |
|---|---|---|
| 20 Nov 2025 | Units released, 475 in the first phase; completion given as 30 Jun 2027 | Agent launch materials |
| Nov 2025 | Some agents list handover as Q4 2027 at launch | Dubai Homes Online |
| 25 Nov 2025 | DLD inspection records 0% | DLD register |
| 1 Dec 2025 | Registered construction start | DLD register |
| 6 Aug 2026 | Estimated completion Q4 2027 | Propsearch |
| 29 Sep 2026 | Register still shows 30 Jun 2027 and the November 2025 inspection | Continental Club |

The date has not moved since launch. The gap between Q2 2027 and Q4 2027 existed from the start, not as a later delay. A registered start of December 2025 and a registered completion date of June 2027 leave a 19 month build window for a 14 storey residential tower on four podium levels.

## What the Binghatti Cullinan handover date means for payments

The plan is 20% on booking, 50% during construction and 30% on handover (Continental Club), which Binghatti also describes as 70/30. On a studio at the launch price of AED 819,999, about AED 246,000 falls due at handover. Binghatti's page now lists studios from AED 867,999 (accessed 1 October 2026), where 30% is about AED 260,000. If handover moves from Q2 2027 to Q4 2027, that payment moves by about six months.

## What to check before relying on the Binghatti Cullinan date

1. **The completion date written in the SPA.** Binghatti's page has no date and portals give two, so the SPA is the one that binds.
2. **A current progress figure.** With no DLD inspection published since November 2025, the DLD project status enquiry service or a written update from Binghatti is the only way to see 2026 progress.
3. **What triggers the final 30%.** Continental Club describes it as due on handover and linked to full completion. The SPA wording sets when Binghatti can call it.

## Frequently asked

### Is Binghatti Cullinan finished?

No. Construction was registered to start on 1 December 2025 and the registered completion date is 30 June 2027. The DLD register still listed it as under construction in late September 2026 (Mitchells Commercial Realty).

### How far along is Binghatti Cullinan?

The only DLD inspection published so far, on 25 November 2025, recorded 0%, a week before the registered construction start. No later inspection had been posted by 1 October 2026. A 70% figure shown on Propsearch reflects the payment plan's construction share, not build progress.

### Is the Binghatti Cullinan handover in Q2 2027 or Q4 2027?

Sources differ. The DLD register via Continental Club and Data Habibi give 30 June 2027, or Q2 2027. Propsearch and several agents list Q4 2027. Mitchells Commercial Realty shows no registered completion date on its copy of the register, dated 15 June 2026.

### Has the Binghatti Cullinan handover date been delayed?

No change has been recorded. Launch materials in November 2025 gave 30 June 2027, and Data Habibi lists the same Q2 2027 target with no postponement. The Q4 2027 dates on some portals were already in use at launch.

## Sources

- Binghatti, Binghatti Cullinan project page, accessed 1 Oct 2026: https://www.binghatti.com/en/projects/binghatti-cullinan
- Continental Club, Binghatti Cullinan (DLD registry data), registry updated 29 Sep 2026: https://continentalclub.ae/project/binghatti-cullinan-al-jaddaf/
- Mitchells Commercial Realty, Binghatti Cullinan DLD registry and registered sales, registry 15 Jun 2026, transactions 28 Sep 2026: https://www.mitchellscommercialrealty.com/off-plan/binghatti-cullinan
- Data Habibi, Binghatti Cullinan, accessed 1 Oct 2026: https://datahabibi.ae/dubai/new-projects/binghatti-cullinan
- Propsearch, Binghatti Cullinan, updated 6 Aug 2026: https://propsearch.ae/dubai/binghatti-cullinan
- LinkedIn (agent post), Grand launch alert, Binghatti Cullinan unit release on 20 November 2025, 21 Nov 2025: https://www.linkedin.com/posts/flyingsparrowsdubai_binghatticullinan-aljaddafdubai-dubairealestate-activity-7397578673966518272-lO59
- Dubai Homes Online, Binghatti Cullinan apartments at Al Jaddaf, 24 Nov 2025: https://www.dubaihomesonline.com/project/1018-binghatti-cullinan-apartments-al-jaddaf-dubai
- DLD, real estate project status enquiry, accessed 1 Oct 2026: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status
