# When is the Bianca by Reportage handover date?

URL: https://www.dxbrealtor.ai/answers/bianca-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Bianca by Reportage has a registered completion date of 31 December 2026 at the Dubai Land Department (DLD), and Reportage markets a Q4 2026 handover. The DLD inspection of 3 June 2026 recorded the community 56.13% complete. About 44% of the work was left seven months before that date, so the timetable is tight. The SPA date and grace period for each unit set the contractual deadline.

## Key figures

- Registered completion date (DLD): 31 Dec 2026 (DLD project 2553, via Mitchell's, registry as at 4 Oct 2026)
- Latest construction progress (DLD): 56.13% (DLD inspection, 3 Jun 2026)
- Developer's stated date: Q4 2026 (Reportage and brokers, accessed 11 Oct 2026)
- Progress a year earlier: 28.36% (Reportage construction update, Jul 2025)

## Bianca by Reportage handover date: the latest position

Bianca's registered completion date at the Dubai Land Department (DLD) is 31 December 2026. Reportage and the brokers selling it give Q4 2026, the same quarter. The register lists the community as project 2553, Bianca, in Wadi Al Safa 2. Prices, sizes and the payment plan: [Bianca by Reportage](/projects/bianca/).

The latest published DLD inspection, on 3 June 2026, recorded 56.13% progress. The date has not moved on the register, but nearly half of the work remained seven months before it.

## Bianca by Reportage handover date by building

The DLD register treats Bianca as one project of 653 townhouses, each ground, two floors and roof. It does not split progress by cluster or phase.

| Project | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Bianca, 653 townhouses | 56.13%, 3 Jun 2026 | 31 Dec 2026 | Q4 2026 (Reportage and brokers); Dec 2026 (Propsearch) |

## How the Bianca by Reportage handover date has changed

| Date | What was recorded | Source |
|---|---|---|
| Jan 2023 | First trace of the project; plot earlier meant for the cancelled Pacific Village | Propsearch |
| 29 Mar 2023 | Launch reported: 653 townhouses, 368 sold within a week | Gulf Construction Online |
| 30 Sep 2023 | Registered construction start | DLD register, via Mitchell's |
| Sep 2024 | 6% complete | Reportage |
| Dec 2024 | 13% complete | Reportage |
| Jul 2025 | 28.36% complete | Reportage |
| 3 Jun 2026 | 56.13% complete; registered completion 31 Dec 2026 | DLD inspection, via Continental Club |
| 4 Oct 2026 | Register still shows 31 Dec 2026 | DLD register, via Mitchell's |

The Q4 2026 handover has been the marketed date since launch, and no public revision had been made by 11 October 2026. Between July 2025 and June 2026 progress rose by about 28 points, roughly 2.5 points a month. Finishing the remaining 44% by 31 December 2026 would take more than six points a month.

## What the Bianca by Reportage handover date means for payments

Most Bianca buyers bought on the standard plan of 10% down, 42% at 1% a month during construction and 48% on handover (Tanami Properties; Excel Properties). Buyers who booked at launch in early 2023 are close to the end of the 42 monthly instalments. The 48% balance waits for completion, so a later handover delays that payment rather than adding new monthly ones. On a 2 bedroom townhouse at the September 2026 resale range of AED 1.02 million to AED 1.37 million (Mitchell's), 48% is about AED 490,000 to AED 658,000.

## What to check before relying on the Bianca by Reportage date

1. **The SPA date and grace period.** The register date is 31 December 2026, but the SPA sets what Reportage must meet and any extra time it is allowed.
2. **The next DLD inspection.** A new figure after 3 June 2026 will show whether the pace has picked up. The DLD project status service publishes each one.
3. **Mortgage timing for the 48% payment.** Banks value the home near completion, so the loan offer depends on when the handover notice is issued.
4. **For an off-plan resale**, the instalments the seller has already paid and how many monthly payments remain before handover.

## Frequently asked

### When will Bianca townhouses be ready?

The registered completion date is 31 December 2026 and the marketed handover is Q4 2026. At the DLD inspection of 3 June 2026 the community was 56.13% complete (Mitchell's, DLD register).

### What is the Bianca Reportage completion date?

31 December 2026 on the DLD register, against a registered start date of 30 September 2023. Propsearch estimates December 2026 and PropertyStellar lists 30 December 2026.

### Has the Bianca handover date been delayed?

Not on the register so far. The DLD record as at 4 October 2026 still shows 31 December 2026, and no revised date had been announced by Reportage. Progress of 56.13% in June 2026 leaves a large share of work for the final months.

### How much is paid at the Bianca handover?

48% of the price under the standard 10/42/48 launch plan, after 10% down and 42% paid at 1% a month (Tanami Properties).

## Sources

- Mitchell's, Bianca (DLD register and registered sales), registry as at 4 Oct 2026, sales to 2 Oct 2026: https://www.mitchellscommercialrealty.com/off-plan/bianca
- Continental Club, projects handing over in 2026 (DLD register), inspection 3 Jun 2026: https://continentalclub.ae/handover-2026/
- Reportage Properties, Bianca project page, accessed 11 Oct 2026: https://reportagegroup.com/projects/residential-communities/bianca/
- Reportage Properties, Bianca construction updates (older site), updates to Jul 2025: https://reportageuae.com/wp-content/plugins/revslider/public/en/project-details/bianca
- Propsearch, Bianca, updated 19 Jun 2026: https://propsearch.ae/dubai/bianca
- PropertyStellar, Bianca in Wadi Al Safa 2, accessed 11 Oct 2026: https://www.propertystellar.com/new-projects/dubai/bianca
- Gulf Construction Online (TradeArabia), Reportage launches 653-unit Dubai residential project, 29 Mar 2023: https://gulfconstructiononline.com/ArticleTA/407951
- Tanami Properties, Bianca townhouses payment plan, accessed 11 Oct 2026: https://www.tanamiproperties.com/Projects/Bianca-Townhouses-PaymentPlan
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status