# When is the Belle Vie by Zimaya handover date?

URL: https://www.dxbrealtor.ai/answers/belle-vie-by-zimaya-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Belle Vie by Zimaya has a registered completion date of 31 March 2028, and Zimaya gives Q1 2028. The Dubai Land Department inspection of 9 September 2026 recorded 11%, up from 1.04% in May 2026. At the pace recorded so far the building would finish after the registered date, so the next inspections are the ones to watch.

## Key figures

- Registered completion date: 31 Mar 2028 (DLD project register via Continental Club)
- Latest construction progress: 11% (DLD inspection, 9 Sep 2026)
- Developer's stated date: Q1 2028 (Zimaya, via Property Finder and Dubai Immo (29 Aug 2025))
- Projection at past year's pace: 21 Sep 2029 (Continental Club estimate, not a developer date)

## Belle Vie by Zimaya handover date: the latest position

Belle Vie by Zimaya is registered with the Dubai Land Department (DLD) for completion on 31 March 2028. Zimaya Properties gives Q1 2028, the quarter it announced at launch in August 2025. Prices, sizes and the payment plan are on the project page: [Belle Vie by Zimaya](/projects/belle-vie-by-zimaya/).

The DLD inspection of 9 September 2026 recorded 11%. The building gained about 10 points in the four months from 8 May 2026, its fastest period so far. To finish by 31 March 2028 it needs about 4.8 points a month over the remaining 18 or 19 months.

## Belle Vie by Zimaya handover date by building

Belle Vie is one building of basement, ground, eight floors and roof, registered as "Belle Vie By Zimaya" with 116 units in Nadd Hessa, the DLD district for Dubai Silicon Oasis (DSO).

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Belle Vie By Zimaya (DLD project 4023, 116 units) | 11% (9 Sep 2026) | 31 Mar 2028 | Q1 2028 (Zimaya, JRE, Impala Real Estate); 31 Mar 2028 (Property Finder) |

## How the Belle Vie by Zimaya handover date has changed

| Date | Event | Source |
|---|---|---|
| 6 Aug 2025 | DLD inspection: 0% | DLD register via Continental Club |
| 29 Aug 2025 | Launch listings: studios from AED 670,000, completion Q1 2028 | Dubai Immo |
| 4 Sep 2025 | Launch reported, over half the building reserved on day one | Gulf News |
| 15 Oct 2025 | Registered construction start; completion registered for 31 Mar 2028 | DLD register via Continental Club |
| 8 May 2026 | DLD inspection: 1.04% | DLD register via Continental Club |
| 9 Sep 2026 | DLD inspection: 11% | DLD register via Continental Club |

The date has not changed since launch. The slow start, about 1 point in the first seven months after the registered construction start, is what puts the date under pressure.

## What the Belle Vie by Zimaya handover date means for payments

Every launch plan took 20% on booking and 30% during construction. On the 50/50 plan, the other 50% falls due on handover. On the 70/30 plan, 20% is due on handover and 30% is paid at 1% a month for 30 months afterwards (Grand Reve Realty). Units sold in late 2026 were offered at 15/15/70, with 70% due on handover (Impala Real Estate). For a studio at the AED 670,000 launch price, the handover payment ranges from AED 134,000 on the 70/30 plan to AED 335,000 on the 50/50 plan.

## What to check before relying on the Belle Vie by Zimaya date

1. **Whether the next DLD reading keeps the May to September pace or improves on it.** The registered date needs close to 5 points a month.
2. **The completion date and grace period in the SPA**, especially on the 15/15/70 plan, where most of the price waits for handover.
3. **When the post-handover instalments begin** on the 70/30 plan, as the 30 monthly payments are counted from the actual handover, not from 31 March 2028.

## Frequently asked

### Is Belle Vie by Zimaya finished?

No. The DLD inspection of 9 September 2026 recorded 11%. The registered completion date is 31 March 2028.

### What is the Belle Vie by Zimaya completion date?

31 March 2028 on the DLD register (project 4023). Zimaya gives Q1 2028 and Property Finder lists 31 March 2028.

### Has the Belle Vie by Zimaya handover date been delayed?

No. The date has been Q1 2028 since the August 2025 launch. Continental Club's projection at the past year's pace reaches 100% on 21 September 2029, but that is an estimate, not a filed change.

### When does the post-handover plan at Belle Vie by Zimaya start?

On the 70/30 plan, 30% is paid at 1% a month for 30 months after handover (Grand Reve Realty), so the schedule starts from the actual handover date.

## Sources

- DLD project register via Continental Club, Belle Vie By Zimaya, inspection 9 Sep 2026; registry updated 8 Oct 2026: https://continentalclub.ae/project/belle-vie-by-zimaya-dubai-silicon-oasis/
- DLD project register via Continental Club, handover 2028 list, accessed 11 Oct 2026: https://continentalclub.ae/handover-2028/
- Gulf News, Belle Vie launches in Dubai Silicon Oasis, 4 Sep 2025: https://gulfnews.com/gn-focus/belle-vie-launches-in-dubai-silicon-oasis-with-exceptional-market-response-1.500256741
- Property Finder, Belle Vie project page, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/zimaya-properties/belle-vie
- Dubai Immo, Belle Vie by Zimaya, 29 Aug 2025: https://dubai-immo.com/en/properties/belle-vie-zimaya-silicon-oasis/
- Grand Reve Realty, Belle Vie payment plans, accessed 11 Oct 2026: https://grandreverealty.com/projects/belle-vie/
- Impala Real Estate, Belle Vie, checked 23 Sep 2026: https://impalarealestate.com/projects/belle-vie/