# When is the Azizi Beach Oasis handover date?

URL: https://www.dxbrealtor.ai/answers/azizi-beach-oasis-handover-date/
Topic: Handover date
Updated: 2026-10-01

## Short answer

Azizi Beach Oasis 2, the phase still to hand over, has a registered completion date of 30 April 2026 on the Dubai Land Department (DLD) register, and Azizi gave Q2 2026 when sales opened in April 2024. The DLD inspection of 7 September 2026 recorded it 53.22% complete, and no revised date has been published. Beach Oasis 1, the first phase, is finished: Azizi began its handover in December 2025.

## Key figures

- Registered completion date, Beach Oasis 2 (DLD): 30 Apr 2026, passed (DLD register, via Mitchells, 23 Sep 2026)
- Latest construction progress, Beach Oasis 2: 53.22% (DLD site inspection, 7 Sep 2026)
- Developer's stated date, Beach Oasis 2: Q2 2026 (Developer supplied, via Continental Club, registry 25 Sep 2026. No revised date published)
- Beach Oasis 1: Handed over (Handover began Dec 2025 (Azizi via TradeArabia, 24 Dec 2025))

## Azizi Beach Oasis handover date: the latest position

Beach Oasis 2, the phase still to hand over, has a registered completion date of 30 April 2026, and that date has passed. The DLD site inspection of 7 September 2026 recorded the project 53.22% complete, and Azizi has not published a revised date. Beach Oasis 1, on the neighbouring plot, is finished and handed over. More on prices and the payment plan is on the [Azizi Beach Oasis](/projects/azizi-beach-oasis/) page.

Progress on phase 2 has been steady but slow against the original date. The DLD recorded 40.65% at its inspection of 3 February 2026 and 53.22% on 7 September 2026, a gain of 12.57 points in about seven months, or roughly 1.8 points a month. Azizi's own figures run lower than the DLD's: it reported 32% on 3 February 2026 and 43% on 22 April 2026, with the structure 99% complete.

## Azizi Beach Oasis handover date by building

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Beach Oasis 2, Tower A | 53.22%, whole project, 7 Sep 2026 | 30 Apr 2026 | Q2 2026 (developer, via Continental Club); Apr 2026 (Property Finder) |
| Beach Oasis 2, Tower B | 53.22%, whole project, 7 Sep 2026 | 30 Apr 2026 | Q2 2026 (developer, via Continental Club); Apr 2026 (Property Finder) |
| Beach Oasis 1 | Complete | Not applicable | Handover began Dec 2025 (Azizi); completed Jan 2026 (Propsearch) |

The DLD register holds Beach Oasis 2 as one project, number 3043, with 704 homes in two towers of 8 floors on a shared 2 basement and ground level. It publishes one progress figure for both towers. Azizi gives the phase 2 mix as 452 studios, 209 one bedroom and 33 two bedroom homes. For phase 1, sources disagree on size: Azizi's handover release counts 762 homes, Propsearch 712.

## How the Azizi Beach Oasis handover date has changed

| Date | What happened | Source |
|---|---|---|
| 14 Oct 2022 | Beach Oasis 1 sales event. | Propsearch |
| 15 Apr 2024 | Beach Oasis 2 booking opened. Registered completion date 30 April 2026. | Property Finder; DLD register |
| May 2024 to Nov 2024 | Phase 1 handover given as Q1 2025, then Q2 2025, then Q3 2025. | Azizi, via Propsearch |
| 17 Nov 2025 | Phase 2 at 18%, structure 69%. | Azizi |
| 24 Dec 2025 | Azizi began handing over Beach Oasis 1. Phase 2 at nearly 20%. | Azizi via TradeArabia |
| 3 Feb 2026 | Phase 2 at 40.65% (DLD inspection); Azizi gave 32% the same day. | DLD register; Azizi |
| 22 Apr 2026 | Phase 2 at 43%, structure 99%. Azizi said it was on schedule. | Azizi |
| 30 Apr 2026 | Registered completion date for phase 2 passed. | DLD register |
| 7 Sep 2026 | Phase 2 at 53.22% (DLD inspection). Register still shows 30 April 2026. | DLD register, via Mitchells and Continental Club |

## What the Azizi Beach Oasis handover date means for payments

Property Finder lists the phase 2 plan as 10% down payment, 40% during construction and 50% on handover. On the AED 604,000 launch price it lists, half the price, AED 302,000, falls due at handover, so the later handover also moves the largest payment later. Phase 1 launched on a different plan, 40% during construction and 60% on handover (Propsearch). With phase 1 handed over, that final 60% has now fallen due for its owners.

## What to check before relying on the Azizi Beach Oasis date

1. **Which phase the unit is in.** Beach Oasis 1 is ready and occupied; a Beach Oasis 2 unit in Tower A or Tower B is still about half built.
2. **The completion date and grace period in the SPA.** The registered date of 30 April 2026 has passed, so the grace period written into the SPA decides what applies until Azizi sets a new date.
3. **Which payment plan the unit was sold on.** The 50% or 60% handover share sets how much is due when keys are released.
4. **The inspection figure for project 3043**, through DLD's project status service. Dubai Handover notes that DLD's daily headline figure for the project showed an invalid 188.8% in September 2026, so the dated inspection figure is the one to read.

## Frequently asked

### When will Azizi Beach Oasis 2 be ready?

No new date has been published. The registered completion date on the DLD register is 30 April 2026, which has passed, and the DLD inspection of 7 September 2026 recorded Beach Oasis 2 at 53.22% complete. Azizi's last update, on 22 April 2026, gave 43% and said the project was on schedule.

### What is the Azizi Beach Oasis completion date?

Beach Oasis 1 is complete. Azizi began its handover in December 2025, and Propsearch records completion in January 2026. Beach Oasis 2 has a registered completion date of 30 April 2026 (DLD project 3043), but was 53.22% built on 7 September 2026.

### Is Azizi Beach Oasis finished?

Phase 1 is finished and occupied. Phase 2, two 8 floor towers with 704 homes, is still under construction, at 53.22% on 7 September 2026 (DLD register, via Continental Club).

### Has the Azizi Beach Oasis handover date been delayed?

Both phases have run late. Phase 1 was first estimated for Q1 2025, revised to Q3 2025 and finished in January 2026 (Propsearch). Phase 2 passed its 30 April 2026 registered completion date at about half built, and the register had not been updated by 25 September 2026.

### How much is due at the Azizi Beach Oasis 2 handover?

Property Finder lists a 10/40/50 plan for phase 2: 10% down payment, 40% during construction and 50% on handover. On the AED 604,000 launch price it lists, the handover payment is AED 302,000 (accessed 1 Oct 2026).

## Sources

- Mitchells Commercial Realty, Beach Oasis 2 DLD registry, registry as at 23 Sep 2026: https://www.mitchellscommercialrealty.com/off-plan/beach-oasis-2
- Continental Club, Beach Oasis 2 (DLD registry data), registry updated 25 Sep 2026: https://continentalclub.ae/project/beach-oasis-2-studio-city/
- Dubai Handover, Beach Oasis 2 (DLD project 3043), accessed 1 Oct 2026: https://dubaihandover.com/projects/3043-beach-oasis-2
- Property Finder, Beach Oasis Phase 2 by Azizi, accessed 1 Oct 2026: https://www.propertyfinder.ae/en/new-projects/azizi-developments/azizi-beach-oasis-2
- Propsearch, Azizi Beach Oasis, updated 5 Feb 2026: https://propsearch.ae/dubai/azizi-beach-oasis
- Propsearch, Azizi Beach Oasis 2, updated 8 Apr 2026: https://propsearch.ae/dubai/azizi-beach-oasis-2
- TradeArabia, Azizi starts handover of 762-unit Dubai Studio City residences, 24 Dec 2025: https://tradearabia.com/News/331742/Azizi-starts-handover-of-762-unit-Dubai-Studio-City-residences
- Middle East News 247, Azizi Developments' Beach Oasis II reaches 18% construction milestone, 17 Nov 2025: https://menews247.com/azizi-developments-beach-oasis-ii-reaches-18-construction-milestone/
- Developers News, Azizi Developments' Beach Oasis II reaches 32% construction milestone, 3 Feb 2026: https://developersnewsmagazine.com/azizi-developments-beach-oasis-ii-reaches-32-construction-milestone/
- Azizi Developments, Beach Oasis II reaches 43% construction milestone, 22 Apr 2026: https://www.azizidevelopments.com/press/azizi-developments-beach-oasis-ii-reaches-43-construction-milestone
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status