# When is the Azha Millennium Residences handover date?

URL: https://www.dxbrealtor.ai/answers/azha-millennium-residences-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Azha Millennium Residences has a registered completion date of 1 September 2027, and Emirates Properties Group's handover target is Q4 2027. The Dubai Land Department inspection of 29 September 2026 recorded the tower 30.07% complete. Its pace in 2026 was about 2.2 points a month, well short of the 4.7 a month needed for December 2027, so the date may move.

## Key figures

- Registered completion date: 1 Sep 2027 (DLD project register via Continental Club)
- Latest construction progress: 30.07% (DLD inspection, 29 Sep 2026)
- Developer's handover target: Q4 2027 (Emirates Properties Group at launch, 14 Jun 2025)
- Portal date: Dec 2027 (Property Finder, accessed 11 Oct 2026)

## Azha Millennium Residences handover date: the latest position

Azha Millennium Residences is registered with the Dubai Land Department (DLD) for completion on 1 September 2027. Emirates Properties Group announced a Q4 2027 completion when it launched the tower in June 2025, and Property Finder lists December 2027. Prices, sizes and the developer's record are on the project page: [Azha Millennium Residences](/projects/azha-millennium-residences/).

The DLD inspection of 29 September 2026 recorded the tower 30.07% complete. It gained 15.45 points in the seven months since the previous inspection on 25 February 2026, about 2.2 points a month. To finish by 1 September 2027, it would need about 6 points a month, and about 4.7 a month for December 2027.

## Azha Millennium Residences handover date by building

Azha Millennium Residences is one tower in JVT District 4, registered by Azha JVT Residences (DLD project number 3482) with 200 units.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Azha Millennium Residences (B+G+4P+30+R, 200 units) | 30.07% (29 Sep 2026) | 1 Sep 2027 | Q4 2027 (developer, Jun 2025); Dec 2027 (Property Finder, Projects Scout) |

## How the Azha Millennium Residences handover date has changed

| Date | Event | Source |
|---|---|---|
| 1 Jun 2025 | Construction start recorded; registered completion 1 September 2027 | DLD via Continental Club |
| 13 Jun 2025 | Launch event; completion given as Q4 2027 | Construction Week, 14 Jun 2025 |
| Oct 2025 | First DLD sales registered | Crown Key |
| 25 Feb 2026 | DLD inspection: about 14.6% | DLD via Continental Club |
| 26 Sep 2026 | Handover still listed as Q4 2027 | Crown Key |
| 29 Sep 2026 | DLD inspection: 30.07% | DLD via Continental Club |

The date has not been changed since launch. The registered date is about a quarter earlier than the developer's quarter. Emirates Properties Group's own updates show its Azha-1 project, forecast to finish on 14 August 2025, at 98.75% on 31 January 2026.

## What the Azha Millennium Residences handover date means for payments

Under the launch plan, buyers pay 10% on booking and 30% during construction, then 10% on handover and the remaining 50% over 36 months after handover (Construction Week, 14 June 2025). The handover date therefore sets two things: when the 10% handover payment is called, and when the three-year post-handover schedule starts. A later handover delays the last instalment by the same amount of time.

## What to check before relying on the Azha Millennium Residences date

1. **The completion date in the SPA**, which may follow the registered 1 September 2027 or the marketed Q4 2027.
2. **The next DLD inspection**, which needs to show a faster pace than the 2.2 points a month recorded in 2026.
3. **How construction instalments are linked**, since the 30% during construction may be tied to dates or to progress milestones.

## Frequently asked

### When will Azha Millennium Residences be completed?

The registered completion date is 1 September 2027 (DLD project register). The developer gave Q4 2027 at launch, and Property Finder lists December 2027.

### Is Azha Millennium Residences finished?

No. It was 30.07% complete at the DLD inspection of 29 September 2026, about 16 months after construction started.

### Has the Azha Millennium Residences handover date been delayed?

Not officially. The Q4 2027 date given at launch in June 2025 still appears on portals, but progress in 2026 was slower than that date needs.

### What is due at Azha Millennium Residences handover?

10% of the price is due on handover, and 50% is then paid over 36 months after handover (Construction Week, 14 Jun 2025).

## Sources

- DLD project register via Continental Club, Azha Millennium Residences, inspection 29 Sep 2026; registry updated 4 Oct 2026: https://continentalclub.ae/project/azha-millennium-residences-jvt-district-4/
- DLD project register via Continental Club, handover 2027 list, accessed 11 Oct 2026: https://continentalclub.ae/handover-2027/
- Construction Week, Emirates Properties launches Azha Millennium Residences, 14 Jun 2025: https://www.constructionweekonline.com/news/azha-millennium-residences-jvt
- Property Finder, Azha Millennium Residences, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/emirates-properties/azha-millennium-residences
- Crown Key, Azha Millennium (DLD record), 26 Sep 2026: https://crownkey.ae/off-plan/azha-millennium/
- Projects Scout, Azha Millennium Residences, accessed 11 Oct 2026: https://www.projectsscout.com/ae/en/project/emirates-properties/azha-millennium-residences
- Emirates Properties Group, Azha construction updates January 2026, 10 Feb 2026: https://www.epgroup.ae/azha-construction-updates-january-2026/