# When is the Artistry One Residences handover date?

URL: https://www.dxbrealtor.ai/answers/artistry-one-residences-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Artistry One Residences has a registered completion date of 9 February 2029, and Select Group gives Q1 2029. The only DLD inspection, on 14 January 2026, recorded 0%, before the registered construction start of 9 February 2026. Artistry Two, the twin tower, carries the same registered date, and one data source shows a later Q4 2029 for Artistry One that the register does not support.

## Key figures

- Registered completion date (DLD): 9 Feb 2029 (DLD register via Continental Club, updated 5 Oct 2026)
- Latest construction progress: 0% (DLD inspection, 14 Jan 2026)
- Developer's stated date: Q1 2029 (Select Group, accessed 11 Oct 2026)
- Other date shown: Q4 2029 (Continental Club developer field, Oct 2026)

## Artistry One Residences handover date: the latest position

Artistry One Residences is registered for completion on 9 February 2029, and Select Group gives Q1 2029 for handover. The register entry is DLD project number 4259, filed by Select Global Development. Full project details are on the [Artistry One Residences](/projects/artistry-one-residences/) page.

Construction had not started when the DLD last inspected the site, on 14 January 2026, and recorded 0%. The register gives 9 February 2026 as the construction start, exactly three years before the registered completion date. No later DLD percentage had been published by 5 October 2026.

## Artistry One Residences handover date by building

Select Group is building two towers under the Artistry name in d3. They are registered as separate projects with the same dates.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Artistry One Residences (36 storeys, 232 units) | 0% (14 Jan 2026) | 9 Feb 2029 | Q1 2029 (Select Group); Q4 2029 (Continental Club developer field) |
| Artistry Two Residences (235 units) | 0% (14 Jan 2026) | 9 Feb 2029 | 2029 (Select Group); Feb 2029 (Property Finder) |

Property Finder describes Artistry Two as a 38 storey tower; Select Group's own page says 37 floors.

## How the Artistry One Residences handover date has changed

| Date | Event | Source |
|---|---|---|
| 14 Jan 2026 | DLD inspection records 0% at both towers | DLD register via Continental Club |
| 15 Jan 2026 | Artistry One registered with DLD | DXB Off Plan |
| 20 Jan 2026 | Private sales open, 1 bedrooms from AED 2.3 million | Insider Real Estate |
| 4 Feb 2026 | Artistry Two launched; handovers "in 2029" | Select Group via Construction Week |
| 9 Feb 2026 | Registered construction start for both towers | DLD register |
| 5 Oct 2026 | Register still shows 9 Feb 2029 | Continental Club |

The date has held since launch. The only outlier is Continental Club's developer field showing Q4 2029 for Artistry One, while its own page for Artistry Two shows Q1 2029.

## What the Artistry One Residences handover date means for payments

The plan is 20% on booking, then 10% within 6, 12 and 18 months, and 50% on handover (EZRE). The construction instalments are tied to time from booking, so a buyer who booked in January 2026 has paid 50% by about July 2027, around 18 months before the registered completion date. The other 50%, about AED 1.15 million on a 1 bedroom at AED 2.3 million, waits for handover. Select Group's site also mentions a 10% booking deposit, so the split can vary by release.

## What to check before relying on the Artistry One Residences date

1. **Which tower the unit is in.** Artistry One is DLD project 4259 and Artistry Two is 4261, with separate escrow records.
2. **The completion date written in the SPA**, given the Q1 2029 and Q4 2029 figures in circulation.
3. **The first DLD inspection after the February 2026 start.** It is the first figure that will show the actual pace.

## Frequently asked

### When will Artistry One Residences be completed?

The registered completion date is 9 February 2029 (DLD register via Continental Club, updated 5 October 2026). Select Group gives Q1 2029.

### When will Artistry Two Residences be handed over?

Artistry Two, DLD project 4261, also has a registered completion date of 9 February 2029 and showed 0% at its 14 January 2026 inspection. Select Group said at its launch on 4 February 2026 that handovers would start in 2029. Property Finder lists it as Artistry Phase 2, completing in February 2029.

### Has the Artistry One Residences handover date changed?

No. Select Group gave Q1 2029 when sales opened in January 2026, and the register holds 9 February 2029. The Q4 2029 on one data page is the only later figure.

### How much is due at handover at Artistry One Residences?

50% of the price. The plan is 20% on booking, 30% during construction and 50% on handover; on a 1 bedroom at AED 2.3 million, that is about AED 1.15 million.

## Sources

- Continental Club, Artistry One Residences (DLD register), registry updated 5 Oct 2026: https://continentalclub.ae/project/artistry-one-residences-dubai-design-district/
- Continental Club, Artistry Two Residences (DLD register), registry updated 5 Oct 2026: https://continentalclub.ae/project/artistry-two-residences-dubai-design-district/
- Continental Club, Dubai projects handing over in 2029 (DLD register), accessed 11 Oct 2026: https://continentalclub.ae/handover-2029/
- Select Group, Artistry One Residences, accessed 11 Oct 2026: https://www.select-group.co/
- Insider Real Estate, Artistry One Residences in Dubai Design District, 20 Jan 2026: https://insider-realestate.com/en/news/artistry-one-residences-dubai-design-district
- Construction Week, Select Group launches Artistry Two Residences in d3, 4 Feb 2026: https://www.constructionweekonline.com/projects-tenders/select-group-d3
- Property Finder, Artistry Phase 2 project page, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/select-group/artistry-phase-2
- DXB Off Plan, Artistry One Residences DLD project record, accessed 11 Oct 2026: https://dxboffplan.com/properties/artistry-one-residences-dubai-design-district/
- EZRE, Artistry One Residences payment plan, accessed 11 Oct 2026: https://ezre.ae/projects/artistry-one-residences/payment-plan