# When is the Altai Tower handover date?

URL: https://www.dxbrealtor.ai/answers/altai-tower-handover-date/
Topic: Handover date
Updated: 2026-10-26

## Short answer

The Altai Tower completion date in the DLD project register is 31 January 2026, and Tiger Properties later set early July 2026 for handover; both dates passed before the build finished. The DLD inspection on 19 October 2026 recorded the tower 100% complete, up from 98.43% on 29 September 2026, and the register changed its status to Ready on 19 October 2026. Tiger said the first residents began collecting keys in the week of 21 September 2026 (Tiger Group, 21 Sep 2026).

## Key figures

- Registered completion date (DLD): 31 Jan 2026 (Passed; construction completed 19 Oct 2026 (DLD register via Continental Club))
- Latest construction progress: 100% (DLD inspection, 19 Oct 2026; status Ready)
- Developer's stated date: Early July 2026 (Tiger delivery schedule, Khaleej Times, 20 Apr 2026)
- Progress in ten months: +34.5 points (65.54% on 29 Dec 2025 to 100% on 19 Oct 2026)

## Altai Tower handover date: the latest position

The DLD project register holds 31 January 2026 as the completion date for Altai Tower, Tiger Properties' 26 floor apartment tower in JVT District 1. That date passed, and so did the early July 2026 handover Tiger gave in its April 2026 delivery schedule, before construction finished. Prices, sizes and payment plans are on the [Altai Tower](/projects/altai-tower/) project page.

The DLD inspection on 19 October 2026 recorded the tower 100% complete, up from 98.43% on 29 September 2026, and the register changed the project status to Ready on 19 October 2026 (DLD register via Continental Club, updated 25 October 2026). Construction is complete on the register. Tiger said the first residents began collecting keys in the week of 21 September 2026 (Tiger Group, 21 Sep 2026).

## Altai Tower handover date by building

Altai Tower is a single building, so one date applies to all 239 registered units.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Altai Tower (DLD project 2636) | 100%, 19 Oct 2026 (status Ready) | 31 Jan 2026 | Early July 2026 (Tiger, Apr 2026); Jan 2026 (Property Finder); Q2 2026 (JRE) |

The developer's DLD filing describes a ground floor, four parking floors and 25 floors of residential and commercial space. Tiger's launch announcement counted 244 homes.

## How the Altai Tower handover date has changed

- **1 June 2023:** Bookings open and registered construction start, with completion set for 31 January 2026 (Property Finder; DLD register).
- **5 June 2023:** Tiger launches Altai and says construction will take three years, with delivery in 2026 (Khaleej Times).
- **8 July 2024:** DLD inspection at 0.74%, a year after the registered start.
- **18 February 2025:** DLD inspection at 13.33%.
- **9 September 2025:** Bayut gives an expected completion of April 2026.
- **29 December 2025:** DLD inspection at 65.54%.
- **31 January 2026:** Registered completion date passes.
- **20 April 2026:** Tiger names early July 2026 for Altai, written "Altay" (Khaleej Times). The DLD inspection a week later, on 27 April 2026, shows 81.61%.
- **11 August 2026:** DLD inspection at 95%.
- **21 September 2026:** Tiger says the first residents are collecting keys this week (Tiger Group).
- **29 September 2026:** DLD inspection at 98.43%. The registered date is still 31 January 2026.
- **19 October 2026:** DLD inspection at 100%; the register changes the project status to Ready.

The delay came from a slow first year. The tower was under 1% built 13 months after the registered start, then went from 13.33% in February 2025 to 100% in October 2026, about 87 points in 20 months. The registered January 2026 date was never revised; keys started about seven and a half months after it, and the July 2026 target slipped by about two and a half months.

## What the Altai Tower handover date means for payments

Most Altai buyers owe a large share at or after handover. On the 20/34/10/36 plan listed by Property Finder, 10% falls due on handover and 36% after it. The Gold Pillars and Bayut plans put 20% or 30% over two years after handover, and the 30/70 plan puts 70% on handover. Because these payments start from handover, the slip from January 2026 to a handover that began in September 2026 has pushed them back by about the same amount.

## What to check before relying on the Altai Tower date

1. **The handover notice from Tiger for the unit**, since the notice, not the register status, sets when keys and the handover payment are due for that unit.
2. **The SPA completion date and grace period**, and any compensation clause, now that the 31 January 2026 date has passed.
3. **The post-handover schedule on the buyer's plan**, to see when the first post-handover instalment falls once handover is confirmed.
4. **The DLD project status for project 2636**, through the DLD project status service, which shows 100% and status Ready from 19 October 2026.

## Frequently asked

### Is Altai Tower JVT finished?

Yes, on the DLD register. The inspection on 19 October 2026 recorded 100%, up from 98.43% on 29 September 2026, and the register changed the status to Ready on 19 October 2026. Tiger said the first residents began collecting keys in the week of 21 September 2026 (Tiger Group, 21 Sep 2026).

### Has the Altai Tower handover date been delayed?

Yes. The registered completion date of 31 January 2026 passed with the tower between 65.54% (December 2025) and 81.61% (April 2026), and the early July 2026 target Tiger gave in April 2026 also passed, with the tower at 95% on 11 August 2026.

### What is the Altai Tower completion date?

31 January 2026 on the DLD register (project 2636). Bayut gave April 2026 in September 2025, and broker sites list Q2 2026 with a construction end of 30 June 2026.

### When will Altay Tower by Tiger be handed over?

Altay is another spelling of Altai Tower. Tiger set early July 2026 in its April 2026 schedule. The DLD register recorded 100% and status Ready on 19 October 2026, and Tiger said the first residents began collecting keys in the week of 21 September 2026.

## Sources

- Tiger Group, Keys change hands at Altai Tower as Tiger Properties completes handover in JVT, 21 Sep 2026: https://www.tigergroup.ae/EventsAndNews
- DLD project register via Continental Club, Altai Tower, inspection 19 Oct 2026; status Ready 19 Oct 2026; registry updated 25 Oct 2026: https://continentalclub.ae/project/altai-tower-jvt-district-1/
- Mitchell's, Altai Tower (DLD project register), registry as at 18 Oct 2026: https://www.mitchellscommercialrealty.com/off-plan/altai-tower
- Real Estate IQ, Altai Tower (DLD register inspection history), DLD register read 13 Oct 2026: https://dubairealestateiq.com/project/altai-tower
- DLD project register via Continental Club, project status Dubai (CC BY 4.0), inspection 29 Sep 2026: https://continentalclub.ae/en/project-status/
- Khaleej Times, Altai Tower launch by Tiger Properties, 5 Jun 2023: https://www.khaleejtimes.com/business/property/altai-tower-launch-a-high-quality-residential-project-by-tiger-properties
- Khaleej Times, Tiger Properties sets Sesilia Tower handover for April 20, unveils 2026 delivery pipeline, 20 Apr 2026: https://www.khaleejtimes.com/business/property/tiger-properties-sets-sesilia-tower-handover-for-april-20-unveils-2026-delivery-pipeline
- Property Finder, Altai Tower project page, accessed 19 Oct 2026: https://www.propertyfinder.ae/en/new-projects/tiger-properties/altai-tower
- Bayut, Altai Tower building guide, 9 Sep 2025: https://www.bayut.com/buildings/altai-tower/
- JRE, Altai Tower by Tiger Group, accessed 19 Oct 2026: https://jre.ae/projects/altai-tower
- Gold Pillars, Altai Tower payment plan, accessed 19 Oct 2026: https://www.goldpillars.ae/project/altai-tower-payment-plan
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status