## Short answer

Alder at Park Five has a registered completion date of 31 December 2027, and Deyaar gives Q4 2027. The DLD inspection of 30 September 2026 recorded 6.07% complete, the first figure above zero. Meeting the date needs about 6.3 points of progress a month from October 2026, far faster than the building has moved so far.

## Key figures

- Registered completion date (DLD): 31 Dec 2027 (DLD project register via Continental Club)
- Latest construction progress: 6.07% (DLD inspection, 30 Sep 2026)
- Developer's stated date: Q4 2027 (Deyaar, 25 Sep 2025; Bayut)
- Date change since launch: None (December 2027 since Sep 2025 (Deyaar))

## Alder at Park Five handover date: the latest position

Alder at Park Five has a registered completion date of 31 December 2027 in the DLD project register, and Deyaar gives Q4 2027. Prices, sizes and the payment plan are on the [Alder at Park Five](/projects/alder-at-park-five/) page.

The DLD inspection of 30 September 2026 recorded 6.07% complete, the first progress above zero. The register shows construction starting on 1 March 2026, so the figure reflects about seven months of work, mostly below ground. To finish by 31 December 2027, the building needs about 6.3 points a month from October 2026. Continental Club's median for completed Dubai projects is about 2.5 points a month, although low-rise buildings like Alder usually move faster once the frame starts.

## Alder at Park Five handover date by building

Alder is a single building, DLD project 4052, with 75 apartments. The table also shows the other Park Five buildings with recent DLD figures, since buyers often compare them.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Alder at Park Five | 6.07%, 30 Sep 2026 | 31 Dec 2027 | Q4 2027 (Deyaar, Bayut) |
| Ivy at Park Five | 6.28%, 17 Sep 2026 | 31 Dec 2027 | Q4 2027 (Deyaar) |
| Neem at Park Five | 15.22%, 9 Sep 2026 | 1 Dec 2027 | Not listed |

Alder and [Ivy](/projects/ivy-at-park-five/) were launched together as the final phase of Park Five and are at almost the same stage.

## How the Alder at Park Five handover date has changed

| Date | What happened | Source |
|---|---|---|
| 21 Aug 2025 | First DLD inspection records 0% | DLD register |
| 25 Sep 2025 | Deyaar announces Ivy and Alder; community completion December 2027 | Deyaar |
| 2 Dec 2025 | Sales open from AED 1.1 million | Offplan Properties |
| 12 Dec 2025 | Bayut lists handover as Q4 2027 | Bayut |
| 1 Mar 2026 | Construction start registered | DLD register |
| 30 Sep 2026 | DLD inspection records 6.07% | DLD register |

The date has stayed at December 2027 throughout. Continental Club's pace estimate, based on only two inspections, is not yet a useful guide to the finish.

## What the Alder at Park Five handover date means for payments

The plan is 10% on booking, 35% during construction and 55% on handover (Bayut; Continental Club). Tanami Properties shows the 35% due within 13 months of booking, so buyers who booked in December 2025 will have paid 45% by early 2027, nearly a year before the registered date. The remaining 55%, about AED 937,000 on the 2 bedroom median of AED 1,703,036, falls due at handover.

## What to check before relying on the Alder at Park Five date

1. **The next DLD inspection.** A figure well above 20% by early 2027 would support the December 2027 date.
2. **The SPA completion date and grace period,** which apply if the building finishes after 31 December 2027.
3. **Deyaar's recent timing.** [Regalia](/projects/regalia-by-deyaar/) handed over later than its first target, and [Tria](/projects/tria-by-deyaar/) was handed over in October 2026, after its September 2026 target had passed (Deyaar, 6 October 2026).

## Frequently asked

### Is Alder at Park Five finished?

No. It was 6.07% complete at the DLD inspection on 30 September 2026. The register records construction starting on 1 March 2026.

### What is the Alder at Park Five completion date?

The registered completion date is 31 December 2027. Deyaar and Bayut give Q4 2027.

### Has the Alder at Park Five handover date been delayed?

No. Deyaar's launch announcement of 25 September 2025 gave December 2027 for the community, and the register still shows 31 December 2027.

### Do all Park Five buildings hand over together?

No. Neem has a registered date of 1 December 2027, while Ivy and Alder share 31 December 2027 (DLD project register via Continental Club). Each building is a separate DLD project.

## Sources

- Zawya, Deyaar hands over 711 homes at Tria in Dubai Silicon Oasis (press release), 6 Oct 2026: https://www.zawya.com/en/press-release/companies-news/deyaar-builds-on-its-2026-handover-momentum-with-711-new-homes-at-tria-in-dubai-silicon-oasis-1510991
- DLD project register via Continental Club, Alder at Park Five (inspection 30 Sep 2026), registry updated 7 Oct 2026: https://continentalclub.ae/project/alder-at-park-five-park-five-by-deyaar/
- DLD project register via Continental Club, projects due in 2027, accessed 11 Oct 2026: https://continentalclub.ae/handover-2027/
- DLD project register via Continental Club, Ivy at Park Five (inspection 17 Sep 2026), registry updated 7 Oct 2026: https://continentalclub.ae/project/ivy-at-park-five-park-five-by-deyaar/
- Deyaar, Deyaar unveils the final phase of Park Five community, 25 Sep 2025: https://www.deyaar.ae/en/media_center/deyaar-unveils-the-final-phase-of-park-five-community-in-dubai-production-city/
- Bayut, Alder at Park Five building guide, 12 Dec 2025: https://www.bayut.com/buildings/alder-park-five-impz/
- Offplan Properties, Alder at Park Five, accessed 11 Oct 2026: https://offplan-properties.ae/project/deyaar-leasing/alder-at-park-five
- Tanami Properties, Alder at Park Five payment plan, accessed 11 Oct 2026: https://www.tanamiproperties.com/Projects/Alder-at-Park-Five-PaymentPlan
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status