# When is the 350 Riverside Crescent handover date?

URL: https://www.dxbrealtor.ai/answers/350-riverside-crescent-handover-date/
Topic: Handover date
Updated: 2026-10-06

## Short answer

Sobha gives December 2027 as the handover date for 350 Riverside Crescent, and Property Finder lists an expected completion date of 1 March 2027; the Dubai Land Department (DLD) register has no registered completion date on file. The DLD inspection of 18 August 2026 put construction at 57.85% complete. The tower's first estimate, recorded by Propsearch when building began in May 2024, was May 2026, so the date has already moved by at least ten months.

## Key figures

- Registered completion date (DLD): Not filed (DLD project 3083, register as at 4 Oct 2026)
- Latest construction progress: 57.85% (DLD inspection, 18 Aug 2026)
- Developer's stated date: Dec 2027 (Sobha Riverside Crescent page, accessed 6 Oct 2026)
- First estimate at construction start: May 2026 (Propsearch; Property Finder now lists 1 Mar 2027)

## 350 Riverside Crescent handover date: the latest position

Sobha gives December 2027 as the handover date for 350 Riverside Crescent, a 750 unit tower in Sobha Hartland 2. Property Finder lists an earlier expected completion date of 1 March 2027. The DLD register, under project number 3083, has no registered completion date on file. Prices, sizes and sales are on the [350 Riverside Crescent](/projects/350-riverside-crescent/) page.

The tower is past the halfway point. The DLD inspection of 18 August 2026 recorded 57.85% complete, up 7.78 percentage points from the inspection of 13 May 2026. That is about 2.5 points a month. If that pace held, the remaining 42% would take more than a year, closer to Sobha's December 2027 date than to March 2027.

## 350 Riverside Crescent handover date by building

350 Riverside Crescent is a single building. The table sets it beside the other five Riverside Crescent towers, which are registered separately.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| 350 Riverside Crescent | 57.85%, 18 Aug 2026 | Not filed | Dec 2027 (Sobha); 1 Mar 2027 (Property Finder) |
| 330 Riverside Crescent | 60.37%, 9 Jul 2026 | Not filed | Jun 2027 (Sobha) |
| 320 Riverside Crescent | 56.67%, 24 Aug 2026 | Not filed | Jul 2027 (Sobha) |
| 340 Riverside Crescent | 55.02%, 18 Aug 2026 | Not filed | Dec 2027 (Sobha) |
| 360 Riverside Crescent | 50.67%, 16 Sep 2026 | Not filed | Dec 2027 (Sobha) |
| 310 Riverside Crescent | 50.23%, 9 Sep 2026 | Not filed | Dec 2027 (Sobha) |

DLD figures are via Mitchell's. 350 is the second most advanced of the six, behind 330, yet it shares the latest Sobha date of December 2027.

## How the 350 Riverside Crescent handover date has changed

| Date | What happened | Source |
|---|---|---|
| Oct 2023 | First trace of the project | Propsearch |
| 10 May 2024 | Booking opens; DLD registers construction start. Propsearch records an estimated completion of May 2026 | Property Finder; DLD register; Propsearch |
| 3 Aug 2024 | Broker launch listing gives December 2027, from AED 1.26 million | My Off Plan Investment |
| Q1 2026 | Sobha's own update: 34% complete, slabs on level 46 | Sobha, 9 Apr 2026 |
| 13 May 2026 | DLD inspection: about 50% | DLD register, via Continental Club |
| 14 Jun 2026 | OffplanCompare gives Q1 2027 | OffplanCompare |
| 18 Aug 2026 | DLD inspection: 57.85% | DLD register, via Mitchell's |
| 6 Oct 2026 | Sobha shows December 2027; Property Finder shows 1 March 2027 | Sobha; Property Finder |

## What the 350 Riverside Crescent handover date means for payments

The share due at completion depends on the plan in the SPA. Property Finder lists 20% at launch, 60% during construction and 20% on handover. Continental Club and several brokers list 20% down, 40% during construction and 40% on handover. For a unit bought at the AED 1.26 million launch price, that is AED 252,000 or AED 504,000 due when the tower is complete. Neither version includes payments after handover.

## What to check before relying on the 350 Riverside Crescent date

1. **The anticipated completion date in the SPA**, since the register holds no date and published dates differ by nine months.
2. **The grace period written into the SPA**, which applies on top of whichever date the contract states.
3. **The next DLD inspection for project 3083.** A move well above 60% by the end of 2026 would support an earlier date; a slow rise would point to December 2027.
4. **Which payment plan applies to the unit**, because a 40% handover payment needs more cash or a larger mortgage in 2027 than a 20% one.

## Frequently asked

### What is the 350 Riverside Crescent completion date?

Sobha gives December 2027. Property Finder lists 1 March 2027 and OffplanCompare gave Q1 2027 (14 June 2026). There is no registered completion date on the DLD register for project 3083, so the date in the SPA is the one that binds.

### Is 350 Riverside Crescent finished?

No. The DLD register lists it as under construction, 57.85% complete at the inspection of 18 August 2026.

### Has the 350 Riverside Crescent handover date been delayed?

Propsearch recorded an estimated completion of May 2026 when construction started in May 2024. Sobha now gives December 2027, and a broker listing gave the same December 2027 date in August 2024, so the May 2026 figure may have been an early estimate rather than a promise.

### When will the other Riverside Crescent towers be ready?

Sobha gives June 2027 for 330, July 2027 for 320 and December 2027 for 310, 340, 350 and 360. At DLD inspections between July and September 2026 the six towers ranged from 50.23% (310) to 60.37% (330) complete.

## Sources

- Mitchell's, 350 Riverside Crescent DLD registry (DLD project 3083), registry as at 4 Oct 2026: https://www.mitchellscommercialrealty.com/off-plan/350-riverside-crescent
- Continental Club, 350 Riverside Crescent (DLD registry and transactions), registry updated 5 Oct 2026: https://continentalclub.ae/project/350-riverside-crescent-sobha-hartland-2/
- Sobha Realty, Riverside Crescent, accessed 6 Oct 2026: https://sobharealty.com/properties-in-dubai/sobha-hartland-2/riverside-crescent
- Property Finder, 350 Riverside Crescent project page, accessed 6 Oct 2026: https://www.propertyfinder.ae/en/new-projects/sobha-real-estate-llc/350-riverside-crescent
- Propsearch, 350 Riverside Crescent, updated 27 Aug 2026: https://propsearch.ae/dubai/350-riverside-crescent
- OffplanCompare, Sobha Riverside Crescent series compared, 14 Jun 2026: https://offplancompare.com/insights/sobha-riverside-crescent-series-guide
- Construction progress tracker, Sobha Dubai Q1 2026 update, via topluxuryproperty.com, 9 Apr 2026: https://topluxuryproperty.com/blog/sobha-dubai-construction-update-q1-2026/
- My Off Plan Investment, 350 Riverside Crescent launch listing, 3 Aug 2024: https://myoffplaninvestment.com/property/350-riverside-crescent-at-sobha-hartland-2-by-sobha-realty/
- Mitchell's, Riverside Crescent DLD registry (projects 3067, 3088, 2788, 3082, 3079), accessed 1 Oct 2026: https://www.mitchellscommercialrealty.com/off-plan/developer/sobha-l-l-c
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status